Site Final | 5/13/2010 | 5/20/2010 | 5/17/2010 | A | DONE |
Clint A Smith
|
|
|
|
Site Final | 3/15/2010 | 5/14/2010 | 5/17/2010 | A | DONE |
Clint A Smith
|
|
|
Jeff V. ###-#### (Epstien)
|
DOC - Permit Finaled | 5/17/2010 | 5/17/2010 | 5/17/2010 | P | PASS |
Clint A Smith
|
|
|
|
Site Final | 1/6/2010 | 3/22/2010 | 3/22/2010 | A | CANC |
Clint A Smith
|
|
|
|
Site Final | 3/15/2010 | 3/15/2010 | 3/15/2010 | P | NR |
Clint A Smith
|
|
|
Still need to re-vegitate the North west of the project area. Spoke with Jeffery V. (RP), will be having seed application occcur here by the end of the week. Will re-inspect for a site final in 2 months.
|
Site Final | 1/5/2010 | 1/6/2010 | 1/6/2010 | A | CANC |
Clint A Smith
|
|
|
301
|
General Inspection | 10/30/2009 | 10/30/2009 | 10/30/2009 | P | PART |
Steven Webb
|
|
|
Areas of bare ground still not stabilized, permit cannot be finaled until such time all denuded soils have been completed.
|
BMP Violation | 8/20/2009 | 8/20/2009 | 8/20/2009 | A | PART |
Clint A Smith
|
|
|
Message to RP: Remove silt fence within the storm channel flow. Informed him that barrier are not allowed within concerated flow channels. Will evolve into more serious issues.
|
Conference | 8/13/2009 | 8/13/2009 | 8/13/2009 | P | DONE |
Clint A Smith
|
|
|
Verbal to RP (George): Protect flow channel at the back end of project area. Will re-inspect on site final inspection.
|
General Inspection | 8/6/2009 | 8/6/2009 | 8/6/2009 | P | PART |
Clint A Smith
|
|
|
Discussed with Epstien over no discharge from turbid water is allowed off site with out special provisions. Was told that they will be installing a head gate at the V cut at the out fall at the basin at the South west end of the project area.
|
BMP Violation | 8/6/2009 | 8/7/2009 | 8/6/2009 | A | PASS |
Eric Strole
|
|
|
corrections are complete.
|
BMP Violation | 8/3/2009 | 8/6/2009 | 8/6/2009 | A | FAIL |
Eric Strole
|
|
|
Left writtwn & verbal correction with RP to install proper inlet protecton after water in removed over DI boxes on east side of parking lot. Need to install proper inlet protection for DI boxes on west side of parking lot. If not complete within 24 hrs a stop work will be issued. Will reinspect 8-07-09 am.
|
Complaint Inspection | 8/6/2009 | 8/6/2009 | 8/6/2009 | A | FAIL |
Steven Webb
|
|
|
Received a call from Inspector 308 (Eric) parking lot was flooded with polluants observed going into drop inlets. Contractor had protected some inlets with filter fabric which is not an acceptable form of protection. Informed Eric to write a correction notice and to summarize what is needed and to give them 24-Hour to comply or a stop work order will be presented. Informed primary RP (George S) that all drop inlets will need to be protected with industry acceptable controls or measures and that the on-site inspector will be meeting with him this morning and presenting this correction notice to him. Will follow up.
|
Random Inspection | 8/5/2009 | 8/5/2009 | 8/5/2009 | A | PART |
Clint A Smith
|
|
|
Still workoing on the issue stated within the previous inspection. Will re-inspect on 7/6/09AM
|
BMP Violation | 8/3/2009 | 8/3/2009 | 8/3/2009 | P | FAIL |
Eric Strole
|
|
|
Left verbal correctio with rp to clean gutter pans that still have not been done and protect all DI boxes in parking lot on south side by 8-05-09 pm. Will reinspect 8-06-09 am.
|
BMP Violation | 7/28/2009 | 7/31/2009 | 7/31/2009 | A | PART |
Eric Strole
|
|
|
DI boxes have been cleaned, sweaping going on.
|
Random Inspection | 7/28/2009 | 7/28/2009 | 7/28/2009 | P | FAIL |
Eric Strole
|
|
|
Left verbal correction with rp to clean up trash, gutter pans, dirt & debris off all hard surfaces and maintain DI boxes by 7-30-09 pm. Will reinspect 7-31-09 am.
|
Random Inspection | 6/30/2009 | 6/30/2009 | 6/30/2009 | A | PASS |
Clint A Smith
|
|
|
|
Conference | 5/8/2009 | 5/13/2009 | 5/13/2009 | A | DONE |
Clint A Smith
|
|
|
Wnet over how to achieve a site final Pass.
|
BMP Violation | 4/28/2009 | 5/1/2009 | 5/1/2009 | A | PART |
Clint A Smith
|
|
|
|
General Inspection | 4/28/2009 | 4/28/2009 | 4/28/2009 | P | CANC |
Clint A Smith
|
|
|
Still need to clean up the west side of project area and maintain the storm drain. Giving them till 4/29/09 PM. Will re-inspect on 5/1/09AM.
|
General Inspection | 4/24/2009 | 4/24/2009 | 4/24/2009 | A | FAIL |
Mike Kinnear
|
|
|
sign posted 460 has corrections they are sweeping the side walk & street gutters.
|
General Inspection | 4/22/2009 | 4/23/2009 | 4/23/2009 | P | FAIL |
Clint A Smith
|
|
|
Correction Notice: 1. Clean up all hard surfaces of all sediment and debris within the gutterpan on the perimeter of the project
|
General Inspection | 4/22/2009 | 4/22/2009 | 4/22/2009 | P | FAIL |
Mike Kinnear
|
|
|
460 has corrections
|
General Inspection | 4/22/2009 | 4/22/2009 | 4/22/2009 | A | FAIL |
Clint A Smith
|
|
|
Verbal to RP:(scott) 1. Clean all gutterpans through out the perimeter of project. 2. Fill out ESC sign with all proper information. Will re-inspect on 4/23/09 PM
Stock pile area at the North of project has submitted for an ESC permit and is ready to be picked up.
|
General Inspection | 4/17/2009 | 4/17/2009 | 4/17/2009 | P | CANC |
Clint A Smith
|
|
|
North area of project. (stockpile / screening area).
|
General Inspection | 4/17/2009 | 4/21/2009 | 4/17/2009 | P | FAIL |
Clint A Smith
|
|
|
Verbal to RP & Western Construction: Submitt an application for Erosion and Sediment Control Permit for the area to the north of project area where screening and stock piling of soil is occuring since the area was not addressed with the site developement permit application. Will re-inspect on 4/21/09 PM.
|
General Inspection | 4/17/2009 | 4/17/2009 | 4/17/2009 | A | PART |
Mike Kinnear
|
|
|
sign posted 460 has issues
|
Tracking Control | 4/6/2009 | 4/8/2009 | 4/9/2009 | P | PART |
Clint A Smith
|
|
|
still activily cleanig streets.
|
General Inspection | 4/6/2009 | 4/6/2009 | 4/6/2009 | P | FAIL |
Mike Kinnear
|
|
|
sign posted 460 has corrections
|
Tracking Control | 4/3/2009 | 4/6/2009 | 4/6/2009 | A | FAIL |
Clint A Smith
|
|
|
Correction Notice: 1. Re-establish an approved stabilized cosntruction accessat the south end and the North west end of project. 2. Install energy disapators at the basins that have outlets installed. 3. Clean up all trash debris through out the project area. Will re-inspect on 4/8/09PM.
|
General Inspection | 4/2/2009 | 4/2/2009 | 4/3/2009 | A | FAIL |
Clint A Smith
|
|
|
MEssage to Scott RP to contact me over the pertaining issues: 1. Re-establish stabilized construction access for both the east and south end of project. 2. Clean all hard surfaces of all sediment and debris. 3. protect the inlet to the outlet point in the basin. Will re-inspect on 04/06/09 PM.
|
General Inspection | 3/9/2009 | 3/16/2009 | 3/16/2009 | A | FAIL |
Clint A Smith
|
|
|
Verbal to RP: Still need to address access point at Winco Ct. Will be doing so since work will be starting on the curb cut today.
|
General Inspection | 3/13/2009 | 3/13/2009 | 3/13/2009 | P | FAIL |
Mike Kinnear
|
|
|
sign posted 460 has correction
|
BMP Violation | 3/6/2009 | 3/8/2009 | 3/9/2009 | A | FAIL |
Clint A Smith
|
|
|
80% of issues dealt with. Still need to block off access in Winco Ct. Cleaning all gutterpans on project perimeter. Will re-inspect on 3/16/09 AM.
|
BMP Violation | 3/6/2009 | 3/6/2009 | 3/6/2009 | P | CANC |
Clint A Smith
|
|
|
Moved to 3/09/09 am.
|
Tracking Control | 3/5/2009 | 3/6/2009 | 3/6/2009 | A | FAIL |
Eric Strole
|
|
|
Left verbal correction with RP to maintain construction access & extend to minimize tracking. Maintain all tracking off of project including gutter pans. Maintain all D.I.'s. Address the turbid water discharging from outfall on the West end of Warehouse Rd. Add additional fence at Winco court where vehicles have been driving on & off project or install construction entrance. Recommended that a "Trackout" sign be posted at the exit of project to notify Sub- Contractors. Clint Smith to reinspect.
|
Tracking Control | 3/5/2009 | 3/6/2009 | 3/6/2009 | A | FAIL |
Clint A Smith
|
|
|
Verbal to RP (Scott U.) 1. Maintain access point on and off of project area. Extend to 300ft min. Also install a stabilized access into and out of the construction parking area of the job trailers. 2. Maintain all tracking off of project area with scraping and also STREET SWEEPING. 3. Maintain all D.I. along Winco Ct., Freight St., and also Warehouse Rd. 4. Address the turbid water distcharging from outfall on the West end of Warehouse Rd. 5. Add additional fence panels at Winco court to eliminate people from driving on and off of project. 6. Recommended that a "Trackout" sign be posted at the exit of project to notify Sub- Contractors. Will re-inspect on 3/6/09 4PM today.
|
General Inspection | 3/3/2009 | 3/3/2009 | 3/3/2009 | P | FAIL |
Mike Kinnear
|
|
|
460 has corrections
|
General Inspection | 2/17/2009 | 2/23/2009 | 2/24/2009 | P | FAIL |
Clint A Smith
|
|
|
Verbal to both RP's(George and Scott) 1. Re-stabilize construction access once utility work has been completed on 3/1/09. 2. Maintain concrete washout pit at the east side of project area. 3. Clean all hasd surface on the perimeter of project area. (activily working on at this time) 4. Containerize of remove all trash spoil pile within the project area. (only 2 were found) Will re-inspect on 3/2/09 for completion of violations. Reviewed over the SWPPP with Scott and imformed him on the deficiencies per the C.G.P. part 3.
|
General Inspection | 2/23/2009 | 2/23/2009 | 2/23/2009 | P | FAIL |
Mike Kinnear
|
|
|
sign posted clint has correction & is going to reinspect 2/23/09
|
General Inspection | 2/23/2009 | 2/23/2009 | 2/23/2009 | A | FAIL |
Mike Kinnear
|
|
|
sign posted clint has correction on site he to reinspect 2/23/09
|
General Inspection | 2/20/2009 | 2/20/2009 | 2/20/2009 | A | FAIL |
Mike Kinnear
|
|
|
sign posted clint has a corrections for site & will reinspect 2/23/09
|
Tracking Control | 2/13/2009 | 2/17/2009 | 2/17/2009 | P | FAIL |
Clint A Smith
|
|
|
Verbal to RP (George): 1. Maintain Costruction access. 2. Clean up all hard surfaces along the perimeter of project area. (Sidewalks and gutter pan) Will re-inspect on 2/23/09 PM.
|
Tracking Control | 2/6/2009 | 2/13/2009 | 2/13/2009 | P | CANC |
Clint A Smith
|
|
|
Moved to 2/17/09 PM.
|
Tracking Control | 2/9/2009 | 2/12/2009 | 2/12/2009 | P | CANC |
Clint A Smith
|
|
|
Moved to 2/13/09 PM.
|
Random Inspection | 2/10/2009 | 2/10/2009 | 2/10/2009 | A | FAIL |
Eric Strole
|
|
|
this inspection was done on 2-9-09. excessive tracking on street, gutters along street need to be cleaned, need to maintain construction entrance. spoke with steve webb on issues. clint smith will reinspect on 2-12-09.
|
Site Preparation | 2/3/2009 | 2/6/2009 | 2/6/2009 | A | FAIL |
Clint A Smith
|
|
|
Have closed off majority of the spots where violations were occuring. The area on the west end will be blocked of with chainlink by next week. D. I. maintenance still needs to occur. Also when tracking gets excessive scraping is occuring. Will re-inspect on 2/13/09.
|
Conference | 2/3/2009 | 2/3/2009 | 2/3/2009 | P | DONE |
Eric Strole
|
|
|
this was a training inspection
|
Tracking Control | 2/3/2009 | 2/3/2009 | 2/3/2009 | P | FAIL |
Clint A Smith
|
|
|
Written Correction Notice to RP: Correct all violations by 2/5/09 PM 1. Clean up all sediment off all hard surfaces. 2. Maintain all D.I.'s. 3. Block off all access points onto the project area that are not stabilized by utilizing a barrier type fencing (high visability fence with T-post or chain link fence) Fail ure to comply will result in further enforcement. Which may result in a stop work order. Will re-inspect on 2/6/09AM
Spoke with the RP (George) over the staps that will be taken to correct all of the violations.
|
Conference | 1/30/2009 | 1/30/2009 | 1/30/2009 | P | CANC |
Eric Strole
|
|
|
|
General Inspection | 1/28/2009 | 1/28/2009 | 1/29/2009 | P | CANC |
Bill VanDegrift
|
|
|
|
General Inspection | 1/26/2009 | 1/26/2009 | 1/26/2009 | P | PASS |
Mike Kinnear
|
|
|
sign posted site looks fine
|
General Inspection | 1/22/2009 | 1/22/2009 | 1/22/2009 | P | PASS |
Mike Kinnear
|
|
|
sign posted site looks fine
|
General Inspection | 1/20/2009 | 1/20/2009 | 1/20/2009 | P | PASS |
Mike Kinnear
|
|
|
sign posted site looks fine
|
Tracking Control | 1/20/2009 | 1/20/2009 | 1/20/2009 | A | PART |
Clint A Smith
|
|
|
(Discuused with George the RP). Per confrence call on 1/16/09. Perventitive measure have been put inplace. Since the freeze has occured, will have to wait until the thaw or percipetation to occur to see if the measures taken will work to the local and federal standards.
|
Conference | 1/15/2009 | 1/15/2009 | 1/15/2009 | P | DONE |
Steven Webb
|
|
|
Conference call with Contractor both onsite personnel (George & Jeff) and management (Stu) in Chicago to discuss mud & dirt ongoing tracking issues. Boise City personnel included Angie B., Clint S. & Steve W. Epstein outlined steps which have been taken to reduce tracking to MEP, including extending construction entrance and access roads. As well hourly maintanence is being performed on hard surfaces. City staff exhorted Epstein to take the necessary steps for compliance to BMC 8-17 and their federal permit. Other sediment control options were outlined beyond rock entrances and roadways. These options included washouts and under carriage spray down systems. It was explained that it is their responsibility for compliance. Will follow up periodically.
|
General Inspection | 1/14/2009 | 1/14/2009 | 1/14/2009 | P | FAIL |
Mike Kinnear
|
|
|
460 has correction notice on site
|
Tracking Control | 1/14/2009 | 1/14/2009 | 1/14/2009 | A | FAIL |
Clint A Smith
|
|
|
Notice to RP and Jeff the PM) Correction Notice: Clean all tracking off of the Right-A-Away. Use the MEP to achieve the miniumizing of track off of the project area. Failure to comply will result in further enforcement. Which may result in a stop work order. Will re-inspect on 1/20/09
|
Tracking Control | 1/14/2009 | 1/14/2009 | 1/14/2009 | A | CANC |
Clint A Smith
|
|
|
Duplicate.
|
General Inspection | 1/13/2009 | 1/13/2009 | 1/13/2009 | P | PART |
Mike Kinnear
|
|
|
sign posted tracking sweeper sched.
|
Tracking Control | 1/9/2009 | 1/12/2009 | 1/12/2009 | A | PART |
Clint A Smith
|
|
|
Minor tracking. Sweeper scheduled.
|
Tracking Control | 1/9/2009 | 1/9/2009 | 1/9/2009 | P | DEFR |
Clint A Smith
|
|
|
Moved to 1/12/09
|
General Inspection | 1/8/2009 | 1/8/2009 | 1/8/2009 | P | PASS |
Mike Kinnear
|
|
|
sign posted site looks fine
|
Tracking Control | 1/7/2009 | 1/7/2009 | 1/7/2009 | A | PASS |
Clint A Smith
|
|
|
|
General Inspection | 12/31/2008 | 12/31/2008 | 12/31/2008 | P | PASS |
Mike Kinnear
|
|
|
sign posted site looks fine
|
General Inspection | 12/29/2008 | 12/30/2008 | 12/30/2008 | A | CANC |
Clint A Smith
|
|
|
|
Random Inspection | 12/29/2008 | 12/29/2008 | 12/29/2008 | A | PASS |
Mike Kinnear
|
|
|
sign posted site looks fine
|
General Inspection | 12/28/2008 | 12/29/2008 | 12/29/2008 | A | PASS |
Clint A Smith
|
|
|
Will re-inspect on 12/30/08.
|
General Inspection | 12/22/2008 | 12/22/2008 | 12/22/2008 | P | PASS |
Mike Kinnear
|
|
|
sign posted site looks fine
|
Random Inspection | 12/17/2008 | 12/17/2008 | 12/17/2008 | A | FAIL |
Clint A Smith
|
|
|
EVA access at the north east end should be blocked off by the end of the week. No tracking off of the project due to the freeze conditions.
|
Tracking Control | 11/25/2008 | 12/4/2008 | 12/4/2008 | A | DONE |
Clint A Smith
|
|
|
Went over tracking issues with the RP. Told him his options with the EVA out into the court. He will be putting a gate with a lock. Also told him he needs to clean up tracking out on the main strip of road of the entrance. He will be using his water trucks with the PT sprayers to blast all sediment into the burrow ditch on the south side of the road.
|
Tracking Control | 11/25/2008 | 11/25/2008 | 11/25/2008 | P | FAIL |
Clint A Smith
|
|
|
Perventitive measures hav been put into place. Discussec with the RP on street sweeping into the burrow ditch onto the south end of street where there is no drainage. Will re-inspect on 12/04/08 AM
|
Tracking Control | 11/14/2008 | 11/17/2008 | 11/17/2008 | P | CANC |
Clint A Smith
|
|
|
tracking is still occuring . Will speak with RP once he is back into town.
|
Tracking Control | 11/5/2008 | 11/7/2008 | 11/14/2008 | P | DONE |
Clint A Smith
|
|
|
|
Random Inspection | 11/5/2008 | 11/5/2008 | 11/5/2008 | P | PART |
Steven Webb
|
|
|
George at Winco. BMP's to reduce mud trackout were discussed. Observed tire washing by Concrete truck drivers as they exited. RP needs to lengthen rock entrance. Concrete washout are being used. Overall site is in good shape.
|
Tracking Control | 11/3/2008 | 11/5/2008 | 11/5/2008 | A | FAIL |
Clint A Smith
|
|
|
Correction Notice. Clean up all tracking off of the access area. Also figure out a acceptiable process to eliminate tracking. Amend your plan and swppp to the process of the process. Will re-inspect on 11/07/08 PM
|
General Inspection | 11/2/2008 | 11/3/2008 | 11/3/2008 | A | FAIL |
Clint A Smith
|
|
|
Need to maintain the construction enrtance by appling a larger rock not the 3/4 rock. At least a 2" washed rock. Also need to install a sediment barrier along the west end of the project at the staging area where the slope to the street is over a 2% grade. Clean up any and all tracking onto the paved areas. Will re-inspect on 11/05/08.
|
General Inspection | 10/10/2008 | 10/10/2008 | 10/10/2008 | P | PART |
Steven Webb
|
|
|
Still no sign of high visibility fencing.
|
General Inspection | 10/6/2008 | 10/6/2008 | 10/9/2008 | P | PART |
Clint A Smith
|
|
|
will be getting access control install on Friday. All in all site is good.
|
General Inspection | 9/24/2008 | 9/24/2008 | 9/24/2008 | P | PART |
Clint A Smith
|
|
|
Entrances installed but still need to provide access controls to deliniate the approved construction access.
|
General Inspection | 9/23/2008 | 9/23/2008 | 9/23/2008 | P | PASS |
Mike Kinnear
|
|
|
sign posted site looks fine
|
Conference | 9/19/2008 | 9/19/2008 | 9/19/2008 | A | DONE |
Clint A Smith
|
|
|
|
General Inspection | 9/18/2008 | 9/18/2008 | 9/18/2008 | P | FAIL |
Clint A Smith
|
|
|
Need to install proper construction entrances for project access. Will be meeting with the RP on 9/19/08 to do a site overview of the project.
|
General Inspection | 8/15/2008 | 8/22/2008 | 8/22/2008 | A | PASS |
Clint A Smith
|
|
|
|
Site Preparation | 8/12/2008 | 8/15/2008 | 8/15/2008 | A | PART |
Clint A Smith
|
|
|
Need to move there construction entrance from dirt to dirt to the entrance off of Eiseman Rd. All in all site is good. CAS Will re-inspect on 8/22/08
|
Site Preparation | 8/11/2008 | 8/12/2008 | 8/12/2008 | A | PART |
Clint A Smith
|
|
|
Met with RP (Scott) and went over the EC plan and discussed over the phases of construction and the perventative measures that will be taken. Will re-inpect on 8/15/08. CAS
|