Aging Inspection | 11/23/2010 | 11/23/2010 | 11/23/2010 | | DONE |
Clint A Smith
|
|
|
|
DOC - Permit Finaled | 11/23/2010 | 11/23/2010 | 11/23/2010 | P | PASS |
Clint A Smith
|
|
|
|
Random Inspection | 4/30/2010 | 4/30/2010 | 4/30/2010 | A | PASS |
Bill VanDegrift
|
|
|
|
General Inspection | 2/25/2010 | 2/25/2010 | 2/25/2010 | P | PASS |
Bob Reichert
|
|
|
looked ok
|
General Inspection | 2/10/2010 | 2/11/2010 | 2/11/2010 | A | PASS |
Dixie Fellows
|
|
|
herbert brice..site ok
|
BMP Violation | 1/13/2010 | 1/15/2010 | 1/15/2010 | A | PASS |
Clint A Smith
|
|
|
|
Complaint Inspection | 1/13/2010 | 1/13/2010 | 1/13/2010 | A | FAIL |
Clint A Smith
|
|
|
Correction Notice to RP: 1. Install access controls on the south and east side of project to restrict access trough the disturbed soil. 2. Install sediment barriers per the Boise City Erosion and Sediment Control Field Manual. * Failure to comply, will result in a stop work order. Will re-inspect on 1/15/10 AM>
|
Complaint Inspection | 1/12/2010 | 1/12/2010 | 1/13/2010 | A | PASS |
Clint A Smith
|
|
|
All tracking has been cleaned up and the RP notified all of their sub-contractors that it is not allowed and if it occurs to clean up immeadiately.
|
General Inspection | 12/28/2009 | 12/29/2009 | 12/29/2009 | A | PASS |
Tony Young
|
|
|
|
Random Inspection | 8/31/2009 | 8/31/2009 | 8/31/2009 | P | PASS |
Doug A Poedy
|
|
|
|
Random Inspection | 8/31/2009 | 8/31/2009 | 8/31/2009 | A | PASS |
Daryl Spivey
|
|
|
bmp's and concrete dump in place.site clean............ds
|
General Inspection | 8/19/2009 | 8/19/2009 | 8/19/2009 | A | PASS |
Doug A Poedy
|
|
|
|
BMP Violation | 8/10/2009 | 8/11/2009 | 8/11/2009 | P | PASS |
Clint A Smith
|
|
|
Correction Notice
|
Complaint Inspection | 8/10/2009 | 8/10/2009 | 8/10/2009 | A | FAIL |
Clint A Smith
|
|
|
Message to RP: Correction Notice: 1. Clean up all tracking onto Grace St.. 2. Protect the storm drain inlets to the East and thee West of project with approved drain inlet protection. 3. Re-install sediment barriers by the end of the day. **Failure to comply, will result in a Stop Work Order** Will re-inspect on 8/11/09 PM.
|
Site Preparation | 8/4/2009 | 8/4/2009 | 8/4/2009 | | PASS |
Clint A Smith
|
|
|
|