Site Final | 11/16/2009 | 11/17/2009 | 11/17/2009 | P | PASS |
Tom Arcoraci
|
|
|
|
Random Inspection | 11/6/2009 | 11/6/2009 | 11/6/2009 | A | PASS |
Bill VanDegrift
|
|
|
AtoZ did lawn sprinkler
|
General Inspection | 10/30/2009 | 10/30/2009 | 10/30/2009 | P | PASS |
Bob Reichert
|
|
|
looked ok, landscapers on site
|
Random Inspection | 9/1/2009 | 9/1/2009 | 9/1/2009 | P | PASS |
Jim Storey
|
|
|
c/n made ok
|
Random Inspection | 8/31/2009 | 8/31/2009 | 8/31/2009 | A | FAIL |
Jim Storey
|
|
|
verbal to rp to sweep street.
|
General Inspection | 8/26/2009 | 8/26/2009 | 8/26/2009 | P | PASS |
Bob Reichert
|
|
|
looked ok
|
Random Inspection | 8/26/2009 | 8/26/2009 | 8/26/2009 | A | PASS |
Troy James
|
|
|
site ok
|
General Inspection | 8/20/2009 | 8/20/2009 | 8/20/2009 | P | PASS |
Jack Frank
|
|
|
ok
|
Random Inspection | 6/10/2009 | 6/10/2009 | 6/10/2009 | A | PART |
Jack Frank
|
|
|
|
General Inspection | 6/4/2009 | 6/4/2009 | 6/4/2009 | P | PASS |
Tom Arcoraci
|
|
|
|
Random Inspection | 5/29/2009 | 5/29/2009 | 5/29/2009 | P | PASS |
Tom Arcoraci
|
|
|
|
General Inspection | 5/20/2009 | 5/26/2009 | 5/26/2009 | P | PASS |
Clint A Smith
|
|
|
|
BMP Violation | 5/20/2009 | 5/21/2009 | 5/20/2009 | P | PART |
Clint A Smith
|
|
|
Told RP that they need to provide a washout pit prior to any concrete being poured on project area. Will re-inspect on 5/26/09 Pm
|
Site Preparation | 5/20/2009 | 5/20/2009 | 5/20/2009 | | FAIL |
Clint A Smith
|
|
|
Left message for the applicant (Maria) CORRECTION NOTICE: 1. Provide a valid RP for the project. (Homeowner RP only applies to the promary residency of the property,not an LLC) 2. Post ESC sign at front of project area where it is visable from the street. 3. Provide storm drain protection at the D.I. on the corner of Malad and Shoshone. Failure to comply will result in a STOP WORK ORDER. Will re-inspect on 5/21/09 PM.
|