Permit Information
Permit NumberESC09-00369
StatusFinaled
Name MIKE WALLING
Site Address 12376 W EXECUTIVE DR
Project NameOregon Tile & Marble
Customer Number 
ePlanReview 
Description
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Aging Inspection12/13/201012/13/201012/16/2010 DONE
DetailsMike Jordan
DOC - Permit Finaled12/16/201012/16/201012/16/2010PPASS
DetailsMike Jordan
Final stabalization was completed.
General Inspection10/27/200911/2/200911/2/2009PPASS
DetailsClint A Smith
Area of disturbance check.
General Inspection10/27/200910/27/200910/27/2009PFAIL
DetailsClint A Smith
Verbal RP:
Must ammend the ESC application due to the area of disturbance being greater than what was given to the city. Must be completed by 11/2/09 AM. Will re-inspect on 11/2/09PM.
Random Inspection10/22/200910/22/200910/22/2009PPASS
DetailsMike Jordan
General Inspection10/16/200910/16/200910/16/2009PPASS
DetailsJack Frank
ok
Random Inspection9/28/20099/28/20099/28/2009APASS
DetailsMike Jordan
All outstanding items have been repaired. ok.
BMP Violation9/21/20099/24/20099/24/2009ANR
DetailsClint A Smith
General Inspection9/21/20099/21/20099/21/2009PFAIL
DetailsClint A Smith
Verbal to RP:
1. Install perimeter sediment barrier along the north end of project area where slope is over a 2% grade.
2. Provide cover over the irragation grid at the North west corner of project.
3. Prior to a storm event or when grade is elevated install approved storm drain inlet protection on ALL storm drains through out project.
4. Maintain and re-install concrete washout ara with a top dressing of 2in plus drain rock for access to wahout pit.
Will re-inspect on 9/24/09 AM.
Random Inspection8/18/20098/18/20098/18/2009APASS
DetailsMike Jordan
ESC permit sign posted. BMP's in place. Construction enterance is being maintained. No trackout noted. General site conditions were good.
Random Inspection7/8/20097/8/20097/8/2009PPART
DetailsClint A Smith
Told RP to maintain construction exit at the end of the day and sweep up hard surface.
Site Preparation7/6/20097/6/20097/6/2009 PASS
DetailsClint A Smith
General Inspection6/29/20097/2/20097/2/2009APASS
DetailsClint A Smith
General Inspection7/1/20097/1/20097/1/2009PPASS
DetailsClint A Smith
Site Preparation6/29/20096/29/20096/29/2009APART
DetailsClint A Smith
Verbal to RP:
Recommended to deliniate area of disturbance with T-post and high visability construction fence.
Also requiring protection surrounding the irragation pipe vertical opening at the north west end of project. ALso required strm drain inlet protection on the one inlet in the parking lot to the west infront of bay 2. Wil re-inspect on 7/2/09 AM.