Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberESC09-00451
StatusFinaled
Name DAN CLARK
Site Address 4336 N FIVE MILE RD
Project Nametownhouse
Customer Number 
ePlanReview 
Description
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final2/26/20102/26/20102/26/2010PPASS
DetailsJim Sly
Dan phone
DOC - Permit Finaled2/26/20102/26/20102/26/2010PPASS
DetailsJim Sly
Site Final2/11/20102/11/20102/11/2010PNR
DetailsJim Sly
Need to complete landsc.....
Random Inspection10/28/200910/30/200910/30/2009APASS
DetailsJim Sly
Random Inspection10/28/200910/29/200910/29/2009APASS
DetailsJim Sly
Site Preparation10/28/200910/29/200910/29/2009ACANC
DetailsJim Sly
Dan
Random Inspection10/28/200910/28/200910/28/2009PCANC
DetailsJim Sly
Dan
Random Inspection10/23/200910/29/200910/28/2009ACANC
DetailsJim Sly
Dan phone
Random Inspection10/22/200910/29/200910/28/2009ACANC
DetailsJim Sly
Dan phone
Random Inspection10/28/200910/29/200910/28/2009ACANC
DetailsJim Sly
Dan phone
Random Inspection10/23/200910/23/200910/23/2009PCANC
DetailsJim Sly
Dan phone
Random Inspection10/22/200910/22/200910/22/2009PFAIL
DetailsJim Sly
Talked to Dan RP ........ Landscaping area involved with Prev.C/N.....re-inspect 10/29
Site Preparation10/21/200910/21/200910/21/2009AFAIL
DetailsJim Sly
Verb...RP....sweep, waddles, trash.
General Inspection9/1/20099/1/20099/1/2009PPASS
DetailsEric Strole
per steve webb, need to install a concrete washout pryer to next pour.
Site Final9/1/20099/2/20099/1/2009ACANC
DetailsEric Strole
BMP Violation8/27/20098/28/20098/28/2009AFAIL
DetailsEric Strole
left verbal & written correction with rp that a stop work has been issued till all corrections are complete. install a concrete washout pit. put concrete spoil piles in washout pit. install wattles in front where over 2 percent grade & clean up tracking.
INSP - Stop Work Order8/28/20098/28/20098/28/2009PFAIL
DetailsEric Strole
left verbal & written correction with rp that a stop work has been issued till all corrections are complete. install a concrete washout pit. put concrete spoil piles in washout pit. install wattles in front where over 2 percent grade & clean up tracking.
General Inspection8/27/20098/27/20098/27/2009AFAIL
DetailsSteven Webb
Verbal and written to RP: Install a proper washout pit and install perimeter control (sediment barrier) on downslope. Observed concrete washout had occurred and was on the hard surface. Complete controls by noon of 8/28/09 or a stop work order will be issued.
BMP Violation8/24/20098/27/20098/27/2009AFAIL
DetailsEric Strole
Sediment barriers at front of lot.-left verbal & written correction with rp to install sediment barriers in front where over 2 percent grade & provide concrete washout pit. concrete trucks are washing out on ground. if not complete within 24 hrs a stop work may be issued.
Site Preparation8/24/20098/24/20098/24/2009 FAIL
DetailsClint A Smith
Message to RP:
Install a sediment barrier along the front of lots, due to the fact of slope to the access pave area is over a 2% grade slope. Will be re-inspected on 8/27/09 AM.
Site Preparation8/19/20098/20/20098/20/2009APASS
DetailsJim Sly
Dan ###-####