Site Final | 10/26/2010 | 10/26/2010 | 10/26/2010 | P | PASS |
Jim Sly
|
|
|
|
DOC - Permit Finaled | 10/26/2010 | 10/26/2010 | 10/26/2010 | P | PASS |
Jim Sly
|
|
|
|
DOC - Permit Finaled | 10/26/2010 | 10/26/2010 | 10/26/2010 | P | PASS |
Jim Sly
|
|
|
|
Site Preparation | 3/26/2010 | 3/26/2010 | 3/26/2010 | P | PASS |
Jim Sly
|
|
|
Kirk phone
|
Site Preparation | 3/23/2010 | 3/24/2010 | 3/24/2010 | A | FAIL |
Jim Sly
|
|
|
Talked to Zach (RP) Plan shows Concrete wash out pit location. No washout pit installed. C/N .....Do not pour any concrete without concrete washout pit installed.
|
Site Preparation | 2/16/2010 | 2/16/2010 | 2/19/2010 | | PASS |
Clint A Smith
|
|
|
|
Site Final | 2/17/2010 | 2/18/2010 | 2/18/2010 | A | CANC |
Jim Sly
|
|
|
Called Wright Bros......they are still getting Bids to start project.
|