General Inspection | 12/22/2010 | 12/22/2010 | 12/22/2010 | | DONE |
Clint A Smith
|
|
|
All work completed. Permit was finalled.
|
DOC - Permit Finaled | 12/22/2010 | 12/22/2010 | 12/22/2010 | P | PASS |
Clint A Smith
|
|
|
|
BMP Violation | 4/2/2010 | 4/5/2010 | 4/5/2010 | P | PASS |
Clint A Smith
|
|
|
|
Complaint Inspection | 4/2/2010 | 4/2/2010 | 4/2/2010 | P | FAIL |
Clint A Smith
|
|
|
Correction Notice: 1. Clean up all tracking off of project area onto the street. 2. Install a sediment barrier along the drainiage swale located to the south of lot. Failure to comply will result in further enforcement. Will re-inspect on 4/5/10PM
|
General Inspection | 3/19/2010 | 3/19/2010 | 3/22/2010 | P | PASS |
Tony Young
|
|
|
|
General Inspection | 3/17/2010 | 3/17/2010 | 3/17/2010 | A | PASS |
Dixie Fellows
|
|
|
called joe to clean up trash..will check thurs am
|
Random Inspection | 2/18/2010 | 2/18/2010 | 2/18/2010 | A | PASS |
Daryl Spivey
|
|
|
site clean...........ds
|
Site Preparation | 2/17/2010 | 2/17/2010 | 2/17/2010 | | PART |
Clint A Smith
|
|
|
Verbal to RP: Needs additional silt fence along the south east endof lot where project is next to a storm basin.
|
Site Preparation | 2/12/2010 | 2/12/2010 | 2/12/2010 | P | PASS |
Tony Young
|
|
|
|