Permit Information
Permit NumberESC10-00186
StatusFinaled
Name JAMES LARKIN
Site Address 550 S MAPLE GROVE RD
Project NamePine Tree Subdivision #3
Customer Number 
ePlanReview 
Description
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled11/30/201211/30/201211/30/2012PPASS
DetailsClint A Smith
Aging Inspection10/15/201210/15/201210/15/2012 PART
DetailsKimberly M. Johnson
Silt fence along Shoup not trenched and backfilled; slope does not exceed 2% -ok
Aging Inspection8/13/20128/14/20128/14/2012 PART
DetailsKimberly M. Johnson
Trackout needs cleaned up and maintained as neccessary. RP will be installing access controls. Had conversation with RP about future requirements stabilization for non-active stockpiles.
Aging Inspection2/12/20122/12/20122/12/2012 CANC
DetailsClint A Smith
Weekend
Aging Inspection12/12/201112/12/201112/12/2011 PASS
DetailsMike Jordan
Aging Inspection6/6/20116/6/20116/7/2011 DONE
DetailsJack Frank
BMP Violation4/5/20114/7/20114/7/2011APASS
DetailsClint A Smith
BMP Violation3/31/20114/5/20114/5/2011AFAIL
DetailsClint A Smith
Correction Notice:
Remove or maintain all high visabilty fence along Shoup Ave. Failure to comply within the given time frame will result in further enforcement. Will re-inspect on 4/7/2011AM.
Site Preparation3/29/20113/31/20113/31/2011APART
DetailsClint A Smith
Message to RP:
Still need to remove or re-install the access controls on Shoup st. Waiting on a time frame when it will be complete. Will re-inspect on 4/5/2011
BMP Violation3/24/20113/29/20113/29/2011ADONE
DetailsClint A Smith
Confrence with RP:
1. Maintain the access control along Shoup.
2. Add additional rock for access to the washout pit and maintain the washout pit due to being over 50% capacity.
3. Clean upp all hard surfaces in the active vertical constrution area on a daily basis. Will re-inspect on 3/ 31/2011
BMP Violation3/24/20113/24/20113/24/2011PFAIL
DetailsClint A Smith
Verbal to RP:
Maintain high visablity fence along Shoup st.
In the active verical construction maintain all storm drain inlets. Will re-inspect on 3/29/2011
General Inspection1/31/20111/31/20111/31/2011 PASS
DetailsClint A Smith
General Inspection ESC11/30/201011/30/201011/30/2010 PASS
DetailsClint A Smith
General Inspection ESC9/28/20109/28/20109/28/2010 PART
DetailsMike Jordan
General site conditions ok. Trash is being picked up. No site work at present, noted 4 lots under construction. construction lots are being monitored and inspected.
General Inspection ESC9/28/20109/28/20109/28/2010 CANC
DetailsClint A Smith
Duplicate
General Inspection7/14/20107/29/20107/29/2010ACANC
DetailsClint A Smith
Due the submittal of the townhomes the rule will be extended.
General Inspection ESC7/14/20107/14/20107/14/2010 PART
DetailsClint A Smith
Will be inspecting 14 days for status of activity on the project. NO activity is not present as of today.
Random Inspection5/14/20105/14/20105/14/2010PPART
DetailsSteven Webb
Overall site looks ok, misc. minor controls could be better, e.x. repair construction fencing, other misc access controls could be put in place. Washout pit ok, trash management is ok.
Tracking Control5/3/20105/5/20105/5/2010PPASS
DetailsClint A Smith
BMP Violation5/3/20105/3/20105/3/2010PFAIL
DetailsClint A Smith
Verbal to RP:
Install access controls on the north west side of the project area or a stabilized construction exit. Also install access controls on the south east side of project area to delineate next to the stabilized construction exit. Will re-inspect on 05/5/10PM.
Site Preparation5/3/20105/3/20105/3/2010PPART
DetailsSteven Webb
Project needs access controls and misc debris management.
BMP Violation4/2/20104/5/20104/5/2010APASS
DetailsClint A Smith
BMP Violation4/1/20104/2/20104/2/2010AFAIL
DetailsClint A Smith
Correction Notice to RP verbally
Clean up all hard surfaces of all sediment and debris.
Install inlet protection into the new storm drain inlets at the East end of project area.
Fail ure to comply will result in further enforcement. Will re-inspect on 4/5/10am
BMP Violation4/1/20104/1/20104/1/2010PFAIL
DetailsClint A Smith
Verbal to RP:
Clean up all tracking off of disturbed area. Protect all new storm drains that are active (2).
Clean up all relocate the concrete washout puit in an area that will not inpact the storm drain system. Will re-inspect on 4/2/10PM.
BMP Violation3/15/20103/17/20103/17/2010APASS
DetailsClint A Smith
Site Preparation3/17/20103/17/20103/17/2010 CANC
DetailsSteven Webb
Duplicate inspection
Tracking Control3/15/20103/15/20103/15/2010PFAIL
DetailsClint A Smith
Verbal to RP:
1. Clean up all tracking out of the starging area.
2. Install a stabilized Construction Exit out of staging area.
3. Maintain concrete washout pit prior to next pour date. Will re-inspect on 3/17/10AM.
Site Preparation3/10/20103/10/20103/10/2010PPASS
DetailsClint A Smith
Per the ammendment to the ESC plan, the site is in good condition. All other BMP's have been addressed and instaalled correctly per industry standards.
Aging Inspection6/13/20126/13/2012   
DetailsMike Jordan
Aging Inspection4/13/20124/13/2012   
DetailsMike Jordan
Aging Inspection10/10/201110/10/2011   
DetailsMike Jordan
Aging Inspection8/8/20118/8/2011   
DetailsMike Jordan