Permit Information
Permit NumberESC10-00778
StatusFinaled
Name SCOTT HAWKER
Site Address 3600 W AMERICANA TER
Project NameTrappers Access Drive
Customer Number 
ePlanReviewNo
Description
Grading & Drainage with site utilities. Road into sub-division. Permit issued for site grading and vertical construction
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final6/26/20137/1/20137/1/2013APASS
DetailsClint A Smith
General Inspection6/26/20136/26/20136/26/2013 DONE
DetailsClint A Smith
Explained to RP to remove all temporary BMP's so the permit can be finaled out. Will re-inspect for a final on 7/1/2013
General Inspection6/11/20136/11/20136/11/2013 PART
DetailsClint A Smith
General Inspection5/27/20135/27/20135/28/2013 CANC
DetailsKimberly M. Johnson
Holiday
General Inspection5/10/20135/10/20135/10/2013 PASS
DetailsClint A Smith
General Inspection4/25/20134/25/20134/25/2013 PASS
DetailsClint A Smith
General Inspection4/10/20134/10/20134/10/2013 DONE
DetailsClint A Smith
No activity
General Inspection3/26/20133/26/20133/26/2013 PASS
DetailsClint A Smith
General Inspection3/11/20133/11/20133/12/2013 PASS
DetailsKimberly M. Johnson
Site has been stabilized. The active portion of site on west side will return to Jay Walker's control when final stabilization is achieved for the surrounding areas of the building.
General Inspection2/22/20132/22/20132/25/2013 PASS
DetailsKimberly M. Johnson
General Inspection2/7/20132/7/20132/7/2013 PART
DetailsKimberly M. Johnson
maintain buffer requirements; replace perimeter controls along stockpiles; stabilize inactive areas.
General Inspection1/23/20131/23/20131/23/2013 PASS
DetailsClint A Smith
No actvitiy on the exterior.
General Inspection1/8/20131/8/20131/8/2013 PASS
DetailsTom Arcoraci
no acivity at this time
General Inspection12/24/201212/24/201212/24/2012 PASS
DetailsClint A Smith
No activity.
General Inspection12/7/201212/7/201212/7/2012 PART
DetailsClint A Smith
clean up sediment off of hardsurfaces
General Inspection11/22/201211/22/201211/23/2012 CANC
DetailsKimberly M. Johnson
Holiday
General Inspection11/7/201211/7/201211/7/2012 PASS
DetailsClint A Smith
General Inspection10/23/201210/23/201210/23/2012 PASS
DetailsClint A Smith
General Inspection10/8/201210/8/201210/9/2012 PART
DetailsKimberly M. Johnson
Some washout on ground. Perimeter control in NE side installed and in good condition
General Inspection9/21/20129/21/20129/21/2012 FAIL
DetailsKimberly M. Johnson
Perimeter control on NE side still needs repair. Runoff to ground from concrete paddle mixers in several locations on NE side.
General Inspection9/6/20129/6/20129/6/2012 PART
DetailsKimberly M. Johnson
Perimeter control on NE side needs repair, unattended equipment fueling, washout will need maintenance prior to placing any concrete. Discussed need to maintain the washout for paint, stucco, mortar, ect
General Inspection8/21/20128/22/20128/22/2012APASS
DetailsKimberly M. Johnson
General Inspection8/15/20128/15/20128/15/2012 PASS
DetailsClint A Smith
General Inspection7/31/20127/31/20127/31/2012 PASS
DetailsClint A Smith
General Inspection7/16/20127/16/20127/16/2012 PASS
DetailsClint A Smith
General Inspection6/29/20126/29/20126/29/2012 PASS
DetailsClint A Smith
General Inspection6/14/20126/14/20126/14/2012 PASS
DetailsClint A Smith
General Inspection5/30/20125/30/20125/31/2012 PASS
DetailsClint A Smith
General Inspection5/15/20125/15/20125/15/2012 PASS
DetailsClint A Smith
General Inspection4/30/20124/30/20124/30/2012 PASS
DetailsClint A Smith
General Inspection4/13/20124/13/20124/16/2012 PASS
DetailsClint A Smith
Wash out was addressed from the previous inspection.
General Inspection3/29/20123/29/20123/30/2012 PASS
DetailsClint A Smith
General Inspection3/14/20123/14/20123/14/2012 PART
DetailsClint A Smith
Need to update the primary RP on the project. Explained to Scott with Morgan to update.
Random Inspection2/28/20122/28/20122/28/2012APASS
DetailsTom Arcoraci
General Inspection2/27/20122/27/20122/28/2012 PASS
DetailsTom Arcoraci
General Inspection2/12/20122/12/20122/12/2012 CANC
DetailsClint A Smith
Weekend
BMP Violation1/23/20121/27/20121/27/2012APART
DetailsClint A Smith
BMP's installed and maintained.
General Inspection1/23/20121/23/20121/23/2012 FAIL
DetailsClint A Smith
Verbal to RP:
Install additional sediment protection along the bottom of the top soil stockpile on the canal side. Maintain the perimeter sediment barriers along the Boise River side of the project. There are two areas where the sediment barrier is either being consumed by the stockpile and another part where there is a gap between the wattles. Will follow up on 1/27/2011 am.
General Inspection1/8/20121/8/20121/9/2012 CANC
DetailsClint A Smith
weekend
General Inspection12/23/201112/23/201112/23/2011 PART
DetailsClint A Smith
Two new stock piles aare on the project from the screening of the exsisting stock pile. No threat to the surrounding water ways. Settlers Canal is at least 75ft or more from the stock piles.
General Inspection12/6/201112/6/201112/6/2011 PART
DetailsClint A Smith
Have began to shape stockpiles and will begin to screen piles in the near future. Have advised the RP; if the project becomes in active for more than 14 days they must temporary or perminately stabilize all disturbed that is in active per permit conditions and federal requirements.
General Inspection11/17/201111/17/201111/17/2011 PASS
DetailsClint A Smith
General Inspection11/2/201111/2/201111/4/2011 PART
DetailsClint A Smith
Verbal to RP:
Maintain the construction access when needed.
General Inspection10/18/201110/18/201110/18/2011 PASS
DetailsClint A Smith
General Inspection10/3/201110/3/201110/4/2011 PASS
DetailsClint A Smith
General Inspection9/16/20119/16/20119/16/2011 PASS
DetailsClint A Smith
Walked the site with the Erosion Control company and verified that all perimeter BMP's along the north site of the project atre installed correctly.
General Inspection9/1/20119/1/20119/1/2011PPART
DetailsClint A Smith
Verbal to RP:
Make sure that all straw wattles are installed per manufactures specifications. Install a temporary construction exit. Will follow up on 9/6/2011am.
Complaint Inspection8/30/20118/30/20118/30/2011APART
DetailsClint A Smith
Verbal to RP:
Due to the clearing and grubbing of the stock pile at the north east section of the project a sediment barrier need tobe installed to protect run off on to the ajacent property. Once the utility work is complete at the access, to provide a stabilized construction exit. Until that time to keep traffic to a minimum. Sweep un any sediment on the hard surface on a daily basis or if needed. Will follow up on 9/1/2011.
Site Preparation8/25/20118/29/20118/29/2011APART
DetailsClint A Smith
Site Preparation8/22/20118/24/20118/25/2011ADONE
DetailsClint A Smith
Confrence:

Went over details of the BMP"S that are and will be required for compliane with the ESC permit with the city. Will follow up on 8/29/2011 for a proper "site preparation".
General Inspection8/22/20118/22/20118/22/2011 NR
DetailsClint A Smith