Site Final | 2/25/2011 | 2/28/2011 | 2/28/2011 | A | PASS |
Tom Arcoraci
|
|
|
|
Random Inspection | 2/25/2011 | 2/25/2011 | 2/25/2011 | P | PASS |
Tom Arcoraci
|
|
|
|
Random Inspection | 2/9/2011 | 2/10/2011 | 2/10/2011 | A | PASS |
Jim Storey
|
|
|
|
Random Inspection | 2/7/2011 | 2/7/2011 | 2/7/2011 | P | PASS |
Jim Storey
|
|
|
|
Random Inspection | 1/24/2011 | 1/24/2011 | 1/24/2011 | P | PASS |
Jim Storey
|
|
|
|
Random Inspection | 1/7/2011 | 1/7/2011 | 1/7/2011 | A | NR |
Jim Storey
|
|
|
|
General Inspection | 1/5/2011 | 1/5/2011 | 1/5/2011 | P | PASS |
Bob Reichert
|
|
|
looked ok
|
Random Inspection | 12/13/2010 | 12/13/2010 | 12/13/2010 | P | PART |
Steven Webb
|
|
|
Verbal to RP, re-install washout pit prior to any further placement of concrete.
|
BMP Violation | 12/10/2010 | 12/13/2010 | 12/13/2010 | A | PASS |
Clint A Smith
|
|
|
ALl issues are corrected.
|
General Inspection | 12/10/2010 | 12/10/2010 | 12/10/2010 | A | FAIL |
Clint A Smith
|
|
|
Messae to RP Install a sediment barrier along the north east side of building. Also along the chainlink fence where equiptment has been traveling on. Will reinspect on 12/13/2010AM.
|
Random Inspection | 12/8/2010 | 12/8/2010 | 12/8/2010 | P | PASS |
Jim Storey
|
|
|
|
General Inspection | 12/7/2010 | 12/8/2010 | 12/8/2010 | P | PASS |
Clint A Smith
|
|
|
|
Random Inspection | 12/7/2010 | 12/7/2010 | 12/7/2010 | P | PASS |
Jim Storey
|
|
|
|
Site Preparation | 12/7/2010 | 12/7/2010 | 12/7/2010 | | FAIL |
Clint A Smith
|
|
|
Correction Notice: Provide an RP who has day to day control over erosion and sediment control. Failure to comply with 24hrs a Stop work order will be issued. Will re-inspect on 12/8/2010AM.
|
Site Preparation | 12/3/2010 | 12/3/2010 | 12/3/2010 | P | PASS |
Jim Storey
|
|
|
|