General Inspection | 6/1/2011 | 6/1/2011 | 6/1/2011 | | DONE |
Clint A Smith
|
|
|
Permit finaled.
|
DOC - Permit Finaled | 6/1/2011 | 6/1/2011 | 6/1/2011 | P | PASS |
Clint A Smith
|
|
|
|
General Inspection | 4/29/2011 | 4/29/2011 | 4/29/2011 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 3/25/2011 | 3/25/2011 | 3/25/2011 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 2/22/2011 | 2/22/2011 | 2/22/2011 | A | PASS |
Tony Young
|
|
|
|
General Inspection | 2/21/2011 | 2/21/2011 | 2/21/2011 | | CANC |
Clint A Smith
|
|
|
Holiday.
|
BMP Violation | 1/20/2011 | 1/21/2011 | 1/21/2011 | P | PASS |
Clint A Smith
|
|
|
|
Complaint Inspection | 1/20/2011 | 1/20/2011 | 1/20/2011 | A | FAIL |
Clint A Smith
|
|
|
Verbal to RP: No issues from what tyhe complaintee indicated. Need to install additional sediment barrier along the hill slope towards Bogus Basin Rd. Pick up all trash debris on a daily basis. Also maintain the storm drain inlet protection. Will re-inspect on 1/21/2011PM.
|
BMP Violation | 1/12/2011 | 1/13/2011 | 1/13/2011 | A | PART |
Clint A Smith
|
|
|
Due to the frozen ground at this time will allow the contractor to do a temporary 2" backfill along the inside portion of the wattle until the groung has thawed enough where they can dig an 2" trench.
|
BMP Violation | 1/11/2011 | 1/12/2011 | 1/12/2011 | P | PART |
Clint A Smith
|
|
|
Verbal to RP: Must istall all sediment barrier per the industry and manufactures specifications. Will re-inspect on 1/13/2011PM.
|
Site Preparation | 1/6/2011 | 1/11/2011 | 1/11/2011 | A | FAIL |
Clint A Smith
|
|
|
Verbal to RP: Must install sediment barriers along the west(back) side and the north side of the project lot. Will re-inspect on 1/12/2011 PM.
|
General Inspection | 1/6/2011 | 1/6/2011 | 1/6/2011 | | NR |
Clint A Smith
|
|
|
|