General Inspection | 7/12/2012 | 7/12/2012 | 7/12/2012 | | DONE |
Clint A Smith
|
|
|
Permit finaled
|
DOC - Permit Finaled | 7/12/2012 | 7/12/2012 | 7/12/2012 | P | PASS |
Clint A Smith
|
|
|
|
General Inspection | 6/27/2012 | 6/27/2012 | 6/27/2012 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 6/12/2012 | 6/12/2012 | 6/12/2012 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 5/28/2012 | 5/28/2012 | 5/28/2012 | | CANC |
Clint A Smith
|
|
|
Holiday
|
General Inspection | 5/11/2012 | 5/11/2012 | 5/11/2012 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 4/26/2012 | 4/26/2012 | 4/30/2012 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 4/11/2012 | 4/11/2012 | 4/11/2012 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 3/27/2012 | 3/27/2012 | 3/27/2012 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 3/12/2012 | 3/12/2012 | 3/12/2012 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 2/24/2012 | 2/24/2012 | 2/24/2012 | | PART |
Clint A Smith
|
|
|
Most area of the permitted area has had a tachifier mulch blend applied on the disturbed soil.
|
General Inspection | 2/9/2012 | 2/9/2012 | 2/9/2012 | | PASS |
Clint A Smith
|
|
|
Lots have had an application of a seed, tachifier and mulch application.
|
General Inspection | 1/25/2012 | 1/25/2012 | 1/26/2012 | | PART |
Clint A Smith
|
|
|
Must stabilize all disturbed soil that is inactive 14 days or greater.
|
General Inspection | 1/10/2012 | 1/10/2012 | 1/10/2012 | | FAIL |
Clint A Smith
|
|
|
Trying to figure out who has placed the top soil on the edge of the alleyway in between Wise Way and Palmaiter st. It is not the General contractor but one of the Vertical home builder for there lots.
|
General Inspection | 12/26/2011 | 12/26/2011 | 12/27/2011 | | PASS |
Clint A Smith
|
|
|
No activity today.
|
General Inspection | 12/1/2011 | 12/1/2011 | 12/1/2011 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 11/16/2011 | 11/16/2011 | 11/16/2011 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 10/28/2011 | 10/28/2011 | 10/31/2011 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 10/13/2011 | 10/13/2011 | 10/13/2011 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 9/28/2011 | 9/28/2011 | 9/28/2011 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 9/13/2011 | 9/13/2011 | 9/13/2011 | | PASS |
Clint A Smith
|
|
|
|
BMP Violation | 8/25/2011 | 8/29/2011 | 8/29/2011 | A | PASS |
Clint A Smith
|
|
|
|
General Inspection | 8/22/2011 | 8/25/2011 | 8/25/2011 | A | FAIL |
Clint A Smith
|
|
|
Verbel to RP: Remove the land bridge accross the sidewalk on Hardesty. Will re-inspect on 8/29/2011 AM. Further will occur if not removed.
|
Tracking Control | 8/19/2011 | 8/22/2011 | 8/22/2011 | P | PART |
Clint A Smith
|
|
|
Verbal to RP: Remove the landbridge off of the sidewalk. Will follow up on 8/25/2011am.
|
General Inspection | 8/19/2011 | 8/19/2011 | 8/19/2011 | | FAIL |
Clint A Smith
|
|
|
Verbal to RP: Remove the landbridge at the intersection of Wise Way and Hardesty and replaace it with a non erodible material. Provide an approved stabilized construction exit. Clean up all sediment off of Wise Way. Will re-inspect on 8/22/2011PM.
|
Tracking Control | 8/2/2011 | 8/4/2011 | 8/4/2011 | A | PASS |
Clint A Smith
|
|
|
|
Conference | 7/29/2011 | 8/2/2011 | 8/2/2011 | A | FAIL |
Clint A Smith
|
|
|
Verbal to RP: Clean up all hard surface of all sediment and debris on a daily basis. Will follow up on 8/4/2011.
|
General Inspection | 7/29/2011 | 7/29/2011 | 7/29/2011 | | PART |
Clint A Smith
|
|
|
Will have a conference with the RP over other mminor issues.
|
General Inspection | 7/14/2011 | 7/14/2011 | 7/14/2011 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 6/29/2011 | 6/29/2011 | 6/29/2011 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 6/14/2011 | 6/14/2011 | 6/14/2011 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 5/27/2011 | 5/27/2011 | 5/27/2011 | | PASS |
Clint A Smith
|
|
|
|
Tracking Control | 5/9/2011 | 5/12/2011 | 5/12/2011 | A | PASS |
Clint A Smith
|
|
|
|
General Inspection | 5/5/2011 | 5/9/2011 | 5/9/2011 | A | FAIL |
Clint A Smith
|
|
|
Verbal to RP: Maintain the construction exit inthe subdivision. Will follow up on 11/12/2011AM
|
General Inspection | 5/5/2011 | 5/5/2011 | 5/5/2011 | | CANC |
Clint A Smith
|
|
|
Will re-inspect on 5/9/2011AM.
|
Conference | 4/19/2011 | 4/20/2011 | 4/20/2011 | A | PASS |
Steven Webb
|
|
|
Discussion on dewatering: Met with Knife River, (Curtis & Kirk), D. Powell, J. Conger and Inspector 460. Reviewed options on dewatering Sub #4 & #5. Decision was made to divert water to east side of Harris Ranch property through vegetation and then an existing canel with properly sized rock check dam which water will flow prior to flowing into the Boise River. Will follow up.
|
Conference | 4/19/2011 | 4/19/2011 | 4/19/2011 | A | CANC |
Clint A Smith
|
|
|
Completed by Steve Webb
|
General Inspection | 4/19/2011 | 4/19/2011 | 4/19/2011 | P | PASS |
Steven Webb
|
|
|
Review dewatering procedures: Reviewed options with D Powell, will have further discussions on Wed. morning at 9:00 a.m.
|
General Inspection | 4/18/2011 | 4/18/2011 | 4/19/2011 | P | PASS |
Clint A Smith
|
|
|
Went over where project area in there phases. Walked the dewatering and the area where the discharge is. Told the RP to inspect the discharge point into the new Wallings corador for turbidity. If a turbid discharge is occuring to devert the water away from the Wallings corador. All in all, the project areas are in active accept for the area south of Warm Springs Rd. Will become active once the soil becomes dry.
|
Tracking Control | 4/12/2011 | 4/15/2011 | 4/14/2011 | A | PART |
Clint A Smith
|
|
|
Verbal to RP: Clean up all sediment and debris off of the hard surfaces when practible prefferd on a daily basis or if to excessive.
|
Conference | 4/12/2011 | 4/12/2011 | 4/12/2011 | P | FAIL |
Clint A Smith
|
|
|
Verbal to RP: CLean up all sediment and debris off of the hard surface from the project area on both accesses on the project and laydown area. Also provide proper stabilized construction exits Will reinspect on 4/15/2011am.
|
Conference | 4/12/2011 | 4/12/2011 | 4/12/2011 | P | DONE |
Steven Webb
|
|
|
1:30: Met with Knife River, Jeff & Curtis, Construction Manager, (J. Conger), Third party inspector (Phil from Ground FX) and inspector 460. Handed out and reviewed ESC Permit conditions, turbid discharge cannot be released off site, tracking controls needed (two locations), street in need of sweeping and posting of signage (local and federal) needed. Inspector 460 will follow up.
|
General Inspection | 4/19/2011 | 4/19/2011 | | P | |
|
|
|
|