Aging Inspection | 12/7/2011 | 12/7/2011 | 12/14/2011 | | PASS |
Jim Sly
|
|
|
|
Site Final | 12/12/2011 | 12/13/2011 | 12/13/2011 | A | PASS |
Jim Sly
|
|
|
Mark phone
|
DOC - Permit Finaled | 12/13/2011 | 12/13/2011 | 12/13/2011 | P | PASS |
Jim Sly
|
|
|
|
DOC - Permit Finaled | 12/13/2011 | 12/13/2011 | 12/13/2011 | P | PASS |
Jim Sly
|
|
|
|
Site Preparation | 12/11/2011 | 12/12/2011 | 12/12/2011 | A | CANC |
Jim Sly
|
|
|
Re-sched.......
|
Site Final | 10/6/2011 | 10/6/2011 | 10/6/2011 | P | FAIL |
Jim Sly
|
|
|
Jerry ...Need to complete landscaping.
|
BMP Violation | 6/29/2011 | 6/30/2011 | 6/30/2011 | P | PART |
Clint A Smith
|
|
|
Discussed with RP that the stock pile will be removed starting on 7/1/2011AM. They should be complete by the following Tuesday, 7/6/2011. If so, then no protection would be required in that area. Will check on next week.
|
BMP Violation | 6/27/2011 | 6/29/2011 | 6/29/2011 | A | PART |
Clint A Smith
|
|
|
Message to RP. Install a sediment barrier along the stockpile of soil and the storm drainage basin. Will re-inspect on 6/30/2011PM.
|
Site Preparation | 6/28/2011 | 6/28/2011 | 6/28/2011 | P | PASS |
Jim Sly
|
|
|
Washout in pump truck.
|
Site Preparation | 6/27/2011 | 6/27/2011 | 6/27/2011 | | FAIL |
Clint A Smith
|
|
|
Message to RP: Protect the storm drain inlet to the south of project on Shamrock Ave. Also provide a sediment barrier along the fence line on the south section of the project next the storm water drainage pond. Will re-inspect on 6/29/2011AM
|
Aging Inspection | 9/2/2011 | 9/2/2011 | | | |