Site Final | 5/11/2012 | 5/11/2012 | 5/11/2012 | P | PASS |
Jim Storey
|
|
|
|
DOC - Permit Finaled | 5/11/2012 | 5/11/2012 | 5/11/2012 | P | PASS |
Jim Storey
|
|
|
|
Aging Inspection | 5/10/2012 | 5/10/2012 | 5/11/2012 | | DONE |
Jim Storey
|
|
|
|
Complaint Inspection | 3/7/2012 | 3/7/2012 | 3/7/2012 | A | PASS |
Clint A Smith
|
|
|
No issues found. The olny potental issue could be trash containeer needing to be addressed for the reason of being full. RP explained it will be taken care of today. Also proir to painting, concrete, mortar or any other pollutants that could generate a washout out residual. All in all though, the project is compliant with the current BMC8-17.
|
Random Inspection | 2/29/2012 | 2/29/2012 | 2/29/2012 | P | PASS |
Jim Storey
|
|
|
|
BMP Violation | 1/17/2012 | 1/20/2012 | 1/20/2012 | A | PART |
Clint A Smith
|
|
|
Due to saturated soil the wash out has not been dug out.
|
Complaint Inspection | 1/17/2012 | 1/17/2012 | 1/17/2012 | A | FAIL |
Clint A Smith
|
|
|
Verbal correction to RP: Provide a lined concrete washout or a sealed external washout. Clean up all concrete washout residual in the front and back of the lot and remove or relocate to a lined concrete washout pit. Also when vertical construction begins to provide a trash container unit to place all trash debris within. Will follow up on 1/20/2012 AM,
WIll notify the complaintee after he contacts the city on the actions taken.
|
Random Inspection | 1/5/2012 | 1/6/2012 | 1/6/2012 | A | PART |
Jim Storey
|
|
|
need sign rp's # is bogus.
|
Site Preparation | 1/5/2012 | 1/5/2012 | 1/5/2012 | P | PART |
Jim Storey
|
|
|
need sign
|