Permit Information
Permit NumberESC12-00023
StatusFinaled
Name JOHN LAUER
Site Address 5301 N MAPLE GROVE RD
Project Name 
Customer Number 
ePlanReviewNo
Description
Hyatt Wetlands Decentralized Strom Water Treatment Project. Stormwater utility deversion.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection2/26/20142/26/20143/5/2014 PASS
DetailsAndy J. Long
Finaled.
DOC - Permit Finaled3/5/20143/5/20143/5/2014PPASS
DetailsAndy J. Long
Stormwater utilities have been installed. No further construction. Site is in process of stabilization. Will be inspected under ESC12-00036, the permit for the entire project.
General Inspection2/11/20142/11/20142/11/2014 PASS
DetailsAndy J. Long
General Inspection1/27/20141/27/20141/27/2014 PASS
DetailsAndy J. Long
No changes. No corrections required.
General Inspection1/10/20141/10/20141/10/2014 PASS
DetailsAndy J. Long
Stabilization still in progress.
General Inspection12/26/201312/26/201312/26/2013 PASS
DetailsAndy J. Long
May move to Boise Parks Annual ESC permit coverage. No corrections at this time.
General Inspection12/11/201312/11/201312/13/2013 PASS
DetailsAndy J. Long
General Inspection11/26/201311/26/201311/26/2013 PASS
DetailsAndy J. Long
Stabilization on-going, some BMPs remain in place. Construction is complete.
General Inspection11/11/201311/11/201311/12/2013 CANC
DetailsEvan Jenkins
Holiday
General Inspection10/25/201310/25/201310/25/2013 PASS
DetailsAndy J. Long
Construction activity for pump system is complete but ESC BMPs still in place. Keep permit open through rainy season to help keep soil in place for vegetation to grow on the slopes surrounding wetland.
General Inspection10/10/201310/10/201310/10/2013 PASS
DetailsAndy J. Long
Work on McMillan side of Hyatt has ongoing road work by ACHD. No ESC violations at this time.
General Inspection9/10/20139/10/20139/10/2013 CANC
DetailsBill VanDegrift
General Inspection8/26/20138/26/20138/26/2013 PASS
DetailsAlan Hauser
landscaping and parking lot completed
General Inspection8/9/20138/9/20138/9/2013 CANC
DetailsKimberly M. Johnson
General Inspection7/25/20137/25/20137/25/2013 FAIL
DetailsKimberly M. Johnson
Silt Fence needs repair
General Inspection7/10/20137/10/20137/10/2013 FAIL
DetailsKimberly M. Johnson
Silt Fence needs repaired
General Inspection6/25/20136/25/20136/26/2013 FAIL
DetailsKimberly M. Johnson
Silt fence needs maintained
General Inspection6/10/20136/10/20136/13/2013 FAIL
DetailsKimberly M. Johnson
Silt Fence needs repaired at top parking area
General Inspection5/24/20135/24/20135/28/2013 FAIL
DetailsKimberly M. Johnson
No vegie on south side of park (by parking area) and silt fence needs repaired
General Inspection5/9/20135/9/20135/10/2013 PASS
DetailsKimberly M. Johnson
General Inspection4/24/20134/24/20134/24/2013 PASS
DetailsKimberly M. Johnson
Waiting for grass to grow
General Inspection4/9/20134/9/20134/10/2013 PASS
DetailsKimberly M. Johnson
Waiting for the grass to grow
General Inspection3/25/20133/25/20133/26/2013 PASS
DetailsKimberly M. Johnson
no vegetation yet but still temp stabilized
General Inspection3/8/20133/8/20133/8/2013 DONE
DetailsClint A Smith
Waiting on vegitation to become establish.
General Inspection2/21/20132/21/20132/21/2013 PASS
DetailsClint A Smith
Just applied a hydrolic mixture of seed, tackifier, and mulch to stabilize all disturbed soil last week.
General Inspection2/6/20132/6/20132/6/2013 PART
DetailsKimberly M. Johnson
General Inspection1/22/20131/22/20131/22/2013 PART
DetailsClint A Smith
Need to final the out the stabilization requirements once we get though the winter freeze.
General Inspection1/7/20131/7/20131/9/2013 PART
DetailsKimberly M. Johnson
Bid and authorization to hydroseed and mulch has been granted. Will occur when feasible after snow melts.
General Inspection12/21/201212/21/201212/21/2012 PART
DetailsKimberly M. Johnson
Rocks in place for access control. Seed mix and mulch selected for winter application. Date TBD
General Inspection12/6/201212/6/201212/6/2012 PART
DetailsKimberly M. Johnson
Rocks have been placed along edges for access control. Site has not yet been stabilized.
General Inspection11/21/201211/21/201211/27/2012 FAIL
DetailsKimberly M. Johnson
Stabilization not complete. Update on status per PW: 1. License Agreement for placement of barrier rocks in ACHD's right-of-way is being reviewed by City's legal staff.
2. McMillan Road right-of -way will be staked this week.
3. Barrier rocks along the north side of McMillan will be placed starting next Monday. Park's anticipates it will take one week to complete the work.
3. Seed mixture for hydroseed application has been determined.
4. Hydroseeding will occur as soon as a Change Order with The Wetlands Group is executed.
General Inspection11/6/201211/6/201211/6/2012 FAIL
DetailsClint A Smith
Waiting on Public Works and Parks and Rec. to impliment the thier final stabilization plan for the section along McMillan Rd.
General Inspection10/22/201210/22/201210/22/2012 FAIL
DetailsClint A Smith
No controls have been implimented for final stabilization.
General Inspection10/5/201210/5/201210/5/2012 FAIL
DetailsClint A Smith
Waiting on the city to deliniate the disturbed area and use an approved practice to stabilize all disturbed soil.
General Inspection9/20/20129/20/20129/19/2012 PART
DetailsKimberly M. Johnson
Parking area on Orchard final landscaping complete. Interior of park has been hyrdroseeded and mulched. Parking/staging area off of McMillian has not yet been stabilized. Small rills on slope to canal observed. Perimter BMPS in place but does not meet EPA buffer requirement
General Inspection9/5/20129/5/20129/5/2012 FAIL
DetailsKimberly M. Johnson
Met with RP on site. Landscaping in the park is in progress. Temporary stabilization planned for southern lot. GC will place large boulders at edge along road side to limit traffic and spray with a tackifier. Silt fence needs maintained. Rills in the slope adjacent to canal will needed graded out prior to stabilization.
General Inspection8/21/20128/21/20128/21/2012 FAIL
DetailsClint A Smith
Waiting on final stabilization praactice to become initiated for this section of the project due to inactivity.
General Inspection8/3/20128/3/20128/3/2012 FAIL
DetailsClint A Smith
Site has not had tempporary or perminate stabilization methods implimented. Have discuss with the city and ACHD of the requirements of the 2012 CGP regarding stabilization.
General Inspection7/19/20127/19/20127/19/2012 PART
DetailsClint A Smith
Waiting on the city (Parks and Rec.) to come up with a method to stabilized the area in between the road and canal. All area has been unstabilized over 14 days.
General Inspection7/4/20127/4/20127/4/2012 CANC
DetailsClint A Smith
Holiday
General Inspection6/19/20126/19/20126/19/2012 FAIL
DetailsClint A Smith
Must stabilize all disturbed soils and install access control to prevent vehicle from driving across areas where it is disturbed soil.
General Inspection6/4/20126/4/20126/5/2012 PART
DetailsClint A Smith
Temporoary stabilization methods are working correctly. Cannot close permit until the time that they establish perminate stabilization measures.
General Inspection5/18/20125/18/20125/18/2012 PASS
DetailsClint A Smith
General Inspection5/3/20125/3/20125/3/2012 PASS
DetailsClint A Smith
General Inspection4/18/20124/18/20124/19/2012 FAIL
DetailsClint A Smith
Verbal to RP:
Provide sediment barriers along the irragation/ storm water canal where the bank are disturbed and stabilizing tachifier was not hydrolicy applied.
General Inspection4/3/20124/3/20124/3/2012 PASS
DetailsClint A Smith
General Inspection3/19/20123/19/20123/21/2012 PART
DetailsClint A Smith
Work within the project area has been inactive due to the weather conditions.
General Inspection3/2/20123/2/20123/6/2012 PASS
DetailsClint A Smith
General Inspection2/16/20122/16/20122/16/2012 PART
DetailsClint A Smith
No activity atthis time due to waiting on materials. Site is in compliance though.
General Inspection2/1/20122/1/20122/1/2012 PASS
DetailsClint A Smith
Site Preparation1/17/20121/17/20121/17/2012APART
DetailsClint A Smith
Went over the scoe of work with the RP. We will be meeting on 1/23/2012 to go over the project and perventitive measures.
Site Preparation1/15/20121/15/20121/17/2012 CANC
DetailsClint A Smith
Weekend
General Inspection9/25/20139/25/2013   
DetailsJim Sly