Information based on query as of Tuesday, June 25, 2024.
Permit Information
Permit NumberESC12-00036
StatusFinaled
Name BRENT BARNEY
Site Address 5301 N MAPLE GROVE RD
Project NameHyatt Wetland Project
Customer Number 
ePlanReviewNo
Description
Hyatt wetlands decentralization stormwater treatment demonstration project
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection6/2/20146/2/20146/2/2014 DONE
DetailsEvan Jenkins
see final
DOC - Permit Finaled6/2/20146/2/20146/2/2014PPASS
DetailsEvan Jenkins
Vegetation Re-established
No ESC Issues
Biodegradable BMP's still in place, but will eventually degrade down to nothing
Complete
General Inspection5/16/20145/16/20145/16/2014 PASS
DetailsAndy J. Long
Hillside stabilization/revegetation still in progress in southern portion of Hyatt Wetlands. No active construction at this time. No corrections.
General Inspection5/1/20145/1/20145/1/2014 PASS
DetailsAndy J. Long
General Inspection4/16/20144/16/20144/16/2014 PASS
DetailsAndy J. Long
Orange silt fence has been removed as requested along McMillan Road and Settlers Canal. No further construction but there is some remaining slope stabilization in progress. No corrections at this time.
General Inspection4/1/20144/1/20144/1/2014 PASS
DetailsEvan Jenkins
General Inspection3/17/20143/17/20143/17/2014 PASS
DetailsAndy J. Long
No changes or ESC issues observed. The other Hyatt Wetlands project ESC case (ESC12-00023) was finaled. This permit will remain open to remove temporary BMPs and monitor stabilization.
General Inspection2/28/20142/28/20143/5/2014 PASS
DetailsAndy J. Long
No recent changes to Hyatt Wetlands. Some temporary BMPs still remain while slopes throughout project are stabilized. After this spring the orange silt fence along McMillan should be removed.
General Inspection2/13/20142/13/20142/14/2014 PASS
DetailsJim Johnson
General Inspection1/29/20141/29/20141/29/2014 PASS
DetailsAlan Hauser
General Inspection1/14/20141/14/20141/17/2014 PASS
DetailsJim Johnson
General Inspection12/30/201312/30/201312/30/2013 PASS
DetailsAndy J. Long
General Inspection12/13/201312/13/201312/13/2013 PASS
DetailsAndy J. Long
Stabilization in progress. No activity.
General Inspection11/28/201311/28/201311/29/2013 CANC
DetailsEvan Jenkins
Holiday
General Inspection11/13/201311/13/201311/13/2013 PASS
DetailsAndy J. Long
General Inspection10/29/201310/29/201310/29/2013 PART
DetailsEvan Jenkins
Same Comments as Andy
General Inspection10/14/201310/14/201310/14/2013 PART
DetailsAndy J. Long
BMPs are still in place in many areas as part of ongoing stabilization of hillsides in park. BMPs by McMillan Road should be removed if construction is finished. No construction activity.
General Inspection9/27/20139/27/20139/27/2013 PASS
DetailsAndy J. Long
Silt fence is along McMillan is still in place. Construction appears to be finished for the time being. Will check with Parks and then final out
General Inspection9/12/20139/12/20139/13/2013 CANC
DetailsBill VanDegrift
General Inspection8/28/20138/28/20138/29/2013 CANC
DetailsAlan Hauser
General Inspection8/13/20138/13/20138/13/2013 CANC
DetailsKimberly M. Johnson
General Inspection7/29/20137/29/20137/29/2013 FAIL
DetailsKimberly M. Johnson
Repair silt fence at top parking lot.
General Inspection7/12/20137/12/20137/12/2013 FAIL
DetailsKimberly M. Johnson
Silt Fence needs maintenance
General Inspection6/27/20136/27/20136/26/2013 FAIL
DetailsKimberly M. Johnson
maintain silt fence
General Inspection6/12/20136/12/20136/13/2013 FAIL
DetailsKimberly M. Johnson
Silt fence needs repaired at top lot
General Inspection5/28/20135/28/20135/28/2013 FAIL
DetailsKimberly M. Johnson
No vegie on south side of park (by parking area) and silt fence needs repaired
General Inspection5/13/20135/13/20135/15/2013 PART
DetailsKimberly M. Johnson
No vegetation on south side of park yet and silt fence needs maintained.
General Inspection4/26/20134/26/20134/26/2013 PASS
DetailsKimberly M. Johnson
Waiting for vegie
General Inspection4/11/20134/11/20134/12/2013 PASS
DetailsKimberly M. Johnson
waiting for grass to grow
General Inspection3/27/20133/27/20133/27/2013 PASS
DetailsKimberly M. Johnson
Waiting for veg to grow.; temp stabilization in place
General Inspection3/12/20133/12/20133/12/2013 PASS
DetailsKimberly M. Johnson
Remaining areas previously left unstabilized were hydraulically seeded and mulched mid-feb; no vegetative growth yet.
General Inspection2/25/20132/25/20132/25/2013 PART
DetailsClint A Smith
Waiting for vegitation to become established.
General Inspection2/8/20132/8/20132/8/2013 PART
DetailsKimberly M. Johnson
General Inspection1/24/20131/24/20131/24/2013 PART
DetailsClint A Smith
Must wait for the spring to assess the project status inregards to stabilization that is established and what areas needing stabilization measures implimented.
General Inspection1/9/20131/9/20131/9/2013 PART
DetailsKimberly M. Johnson
Bid and authorization to hydroseed and mulch has been granted. Will occur when feasible after snow melts.
General Inspection12/25/201212/25/201212/26/2012 CANC
DetailsClint A Smith
Holiday
General Inspection12/10/201212/10/201212/6/2012 PART
DetailsKimberly M. Johnson
Rocks have been placed along edges for access control. Site has not yet been stabilized.
General Inspection11/23/201211/23/201211/27/2012 FAIL
DetailsKimberly M. Johnson
Stabilization not yet complete. Update per PW: 1. License Agreement for placement of barrier rocks in ACHD's right-of-way is being reviewed by City's legal staff.
2. McMillan Road right-of -way will be staked this week.
3. Barrier rocks along the north side of McMillan will be placed starting next Monday. Park's anticipates it will take one week to complete the work.
3. Seed mixture for hydroseed application has been determined.
4. Hydroseeding will occur as soon as a Change Order with The Wetlands Group is executed.
General Inspection11/8/201211/8/201211/8/2012 PART
DetailsClint A Smith
Site is stabilized with seed and tachifier within the areas of the park its self. Waiting on vegitation to establish to final out the permit.
General Inspection10/24/201210/24/201210/24/2012 PASS
DetailsClint A Smith
General Inspection10/9/201210/9/201210/9/2012 FAIL
DetailsKimberly M. Johnson
Interior slopes of park have been seeded and mulched. Landscaping on north parking parking lot complete. Staging area on south side (off of McMillian) not stabilized. Perimeter controls are in place
General Inspection9/24/20129/24/20129/24/2012 PART
DetailsClint A Smith
All disurbed area have had seed, tach, mulch blend appied initiating final stabilization.
General Inspection9/7/20129/7/20129/5/2012 FAIL
DetailsKimberly M. Johnson
Met with RP on site. Landscaping in the park is in progress. Temporary stabilization planned for southern lot. GC will place large boulders at edge along road side to limit traffic and spray with a tackifier. Silt fence needs maintained. Rills in the slope adjacent to canal will needed graded out prior to stabilization.
General Inspection8/23/20128/23/20128/24/2012 PART
DetailsClint A Smith
SIte will have hydroloic mulch with seed applied to all sloped area in late August or early September.
General Inspection8/8/20128/8/20128/8/2012 PART
DetailsClint A Smith
Need to complete daily clean up of the contruction entrance.
General Inspection7/24/20127/24/20127/24/2012 PASS
DetailsClint A Smith
Most of the slpe have had a seed/tach./mulch application aspplied hydrolically. Slope hav also been broken up with energy disapaters installed along the slope as well.
General Inspection7/6/20127/6/20127/6/2012 PASS
DetailsClint A Smith
General Inspection6/21/20126/21/20126/21/2012 PART
DetailsClint A Smith
Discussed with the RP and city engineer to initiate stabilization measures sooner than later. If a seed application is going to be used, make sure to have an effective plan for watering of the seeded area's to promote growth.
General Inspection6/6/20126/6/20126/7/2012 PART
DetailsClint A Smith
Need to stabilize slopes that are completed with an approved industry method for stabilization.
General Inspection5/22/20125/22/20125/24/2012 PASS
DetailsClint A Smith
General Inspection5/3/20125/3/20125/3/2012 PASS
DetailsClint A Smith
General Inspection4/18/20124/18/20124/19/2012 PART
DetailsClint A Smith
Verbal to RP;
Inspect and add staking to all sediment barriers (composted wattles) where needed.
General Inspection3/30/20123/30/20123/30/2012 PASS
DetailsClint A Smith
General Inspection3/15/20123/15/20123/15/2012 PASS
DetailsClint A Smith
No activity on this portion of the project due weather and site conditions.
General Inspection2/29/20122/29/20123/6/2012 PASS
DetailsClint A Smith
Site Preparation1/26/20121/27/20121/27/2012ANR
DetailsClint A Smith
This portion of the project will not begin until Feb. of 2012.
Site Preparation1/26/20121/26/20121/26/2012 CANC
DetailsClint A Smith
Moved to 1/27/2012
General Inspection2/14/20122/14/2012   
DetailsJim Sly