Site Final | 10/4/2012 | 10/4/2012 | 10/4/2012 | P | PASS |
Jim Storey
|
|
|
|
DOC - Permit Finaled | 10/4/2012 | 10/4/2012 | 10/4/2012 | P | PASS |
Jim Storey
|
|
|
|
Random Inspection | 8/9/2012 | 8/9/2012 | 8/9/2012 | P | PASS |
Jim Storey
|
|
|
|
Random Inspection | 8/6/2012 | 8/6/2012 | 8/6/2012 | A | PASS |
Jim Storey
|
|
|
|
General Inspection | 7/25/2012 | 7/26/2012 | 7/26/2012 | A | PART |
Eric Strole
|
|
|
left verbal correction with rp to post esc sign and clean up trash. rp is on site and taking care of corrections. will reinspect when back in area.
|
BMP Violation | 5/8/2012 | 5/10/2012 | 5/11/2012 | A | PART |
Clint A Smith
|
|
|
Verbal to RP: Install the ssediment barrier per the manufacture specifications.
|
Random Inspection | 5/10/2012 | 5/10/2012 | 5/10/2012 | A | PART |
Jim Storey
|
|
|
wip
|
Site Preparation | 5/9/2012 | 5/9/2012 | 5/9/2012 | P | CANC |
Jim Sly
|
|
|
|
Site Preparation | 5/9/2012 | 5/9/2012 | 5/9/2012 | P | CANC |
Jim Sly
|
|
|
|
Site Preparation | 5/3/2012 | 5/3/2012 | 5/8/2012 | P | FAIL |
Clint A Smith
|
|
|
Verbal to RP: Post ESC where visable from the street. Also install a sediment barrier to protect the irragation lateral box within the project area. The lateral in the front portion of the project is protected as long as the vegitation buffer is not disturbed. Will follow up on 5/10/2012AM.
|
DOC - Permit Finaled | | | 3/8/2012 | | PASS |
Jim Storey
|
|
|
|