Aging Inspection | 11/2/2012 | 11/2/2012 | 11/2/2012 | | DONE |
Clint A Smith
|
|
|
Peermit finaled.
|
DOC - Permit Finaled | 11/2/2012 | 11/2/2012 | 11/2/2012 | P | PASS |
Clint A Smith
|
|
|
|
BMP Violation | 8/28/2012 | 8/29/2012 | 8/30/2012 | A | PASS |
Clint A Smith
|
|
|
concrete
|
BMP Violation | 8/27/2012 | 8/28/2012 | 8/28/2012 | A | FAIL |
Clint A Smith
|
|
|
Verbal to RP: Clean up all concrete wahout in the lot next to the project lot. Will follow up on 8/29/2012AM
|
Site Final | 8/27/2012 | 8/27/2012 | 8/27/2012 | P | PART |
Tom Arcoraci
|
|
|
reveg incomplete
|
Site Final | 8/23/2012 | 8/23/2012 | 8/23/2012 | A | NR |
Dave Hannah
|
|
|
|
General Inspection | 8/10/2012 | 8/10/2012 | 8/10/2012 | A | PASS |
Dixie Fellows
|
|
|
site clean
|
BMP Violation | 6/1/2012 | 6/4/2012 | 6/5/2012 | A | FAIL |
Clint A Smith
|
|
|
Correction Notice: Provide protection for the storm drain inlet infront of the project area. Failure to comply with the notice will result in further enforcement. Wil re-inspect on 6/6/2012AM.
|
Site Preparation | 6/1/2012 | 6/1/2012 | 6/1/2012 | A | FAIL |
Clint A Smith
|
|
|
Verbal to RP: protect the stormdrain within the right away out side of the project area. Will re-inspect on 6/4/2012am
|
Site Preparation | 5/11/2012 | 5/11/2012 | 5/17/2012 | | PEND |
Tony Young
|
|
|
|