General Inspection | 4/18/2013 | 4/18/2013 | 4/19/2013 | | DONE |
Clint A Smith
|
|
|
Permit finaled
|
DOC - Permit Finaled | 4/19/2013 | 4/19/2013 | 4/19/2013 | P | PASS |
Clint A Smith
|
|
|
|
General Inspection | 3/18/2013 | 3/18/2013 | 3/18/2013 | | CANC |
Clint A Smith
|
|
|
|
BMP Violation | 2/15/2013 | 2/15/2013 | 2/15/2013 | A | FAIL |
Clint A Smith
|
|
|
Notified ESC Manager of all of the standing violations. All violations except for perimeter control need to be addressed.
|
BMP Violation | 1/16/2013 | 1/18/2013 | 1/24/2013 | A | FAIL |
Kimberly M. Johnson
|
|
|
Onsite conference held 1/22 with Chris, Amanda and Joe. See conference notes
|
Conference | 1/23/2013 | 1/23/2013 | 1/23/2013 | P | DONE |
Kimberly M. Johnson
|
|
|
Met with Chris, Amanda and Joe to review violations and options for remediation.
|
BMP Violation | 1/2/2013 | 1/9/2013 | 1/16/2013 | P | FAIL |
Kimberly M. Johnson
|
|
|
No progress has been made to correct violations. Correction notice issued and re-inspection scheduled for 1/18/13.
|
General Inspection | 12/24/2012 | 12/24/2012 | 12/24/2012 | | FAIL |
Kimberly M. Johnson
|
|
|
Concrete washout within 50' of ditch and not properly contained. Perimeter control not effectively installed; runoff will drain around wattle and not thru it. Tarps over sand for stabilization need maintenance. Spoke to RP and is no longer contact for project. Need to update RP.
|
Site Preparation | 11/19/2012 | 11/21/2012 | 11/21/2012 | A | CANC |
Clint A Smith
|
|
|
|
General Inspection | 11/19/2012 | 11/19/2012 | 11/19/2012 | | FAIL |
Clint A Smith
|
|
|
Message to RP: Post ESC sign where visable from the front of the building. Will follow up on 11/21/2012
|