Permit Information
Permit NumberESC12-00398
StatusFinaled
Name JAMAL NELSON
Site Address 800 W MAIN ST
Project NameZions Bank
Customer Number 
ePlanReviewNo
Description
This also covers the staging area located at Fairview & 30th (2901 W Main). NOI IDR12BH04.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection4/8/20144/8/20144/8/2014 PASS
DetailsAndy J. Long
Finaled.
DOC - Permit Finaled4/8/20144/8/20144/8/2014PPASS
DetailsAndy J. Long
8th & Main Tower is complete and exterior has been stabilized/cleaned. Offsite staging area has been cleaned with no remaining acitivity.
General Inspection2/21/20142/21/20142/21/2014 CANC
DetailsEvan Jenkins
Fee's Due: No Inspection
General Inspection1/6/20141/6/20141/6/2014 CANC
DetailsEvan Jenkins
Fee's Due Hold
No Inspection
General Inspection11/19/201311/19/201311/19/2013 PASS
DetailsAndy J. Long
No discharges observed. Construction activity mostly inside tower. Surrounding streets and sidewalks do not have significant track out. MS4 drop inlets have filter bages.
General Inspection10/4/201310/4/201310/4/2013 PASS
DetailsAndy J. Long
No ESC violations observed at off-site staging area; on-site work on tower is still progress. Drop inlets have protection on 8th and Main have protection. No illicit discharges or improper storage of materials observed. Approved.
General Inspection8/19/20138/19/20138/27/2013 PART
DetailsBob Archibald
work in progress
General Inspection7/2/20137/2/20137/2/2013 PASS
DetailsClint A Smith
General Inspection5/17/20135/17/20135/17/2013 PASS
DetailsClint A Smith
Conference4/1/20134/1/20134/1/2013ADONE
DetailsKimberly M. Johnson
Met with City ESC Inspector, RP (Jamal,ESI), and ACHD Code Enforcement (Ed) at City Hall to discuss violations. Ed from ACHD indicated the storm drain should be sucked out to clean up residue and will pursue this action. Jamal said he currently has an agreement to discharge this water to the sanitary sewer system and that the illicit discharge was a result of mis-management. All other violations identified on 3/29/13 have been corrected.
General Inspection4/1/20134/1/20133/29/2013 FAIL
DetailsClint A Smith
Inspection performed on 3/29/2013:
Found an illicit discharge of water into the storm drain inlet located at the 8th street side of the project where they were dicharging the primed fire lines out into the gutterpan that was impaired with fire proofing material. Stopped discharge upon inpsection.
Conference2/14/20132/14/20132/14/2013PFAIL
DetailsClint A Smith
Discussed with the RP over the clean out of concrete on the outside of the washout containment area. He explained to me that he will have it cleaned up and will be discussing with the concrete company.
BMP Violation1/28/20131/31/20132/1/2013APART
DetailsClint A Smith
At the time of the inspection I notified the RP that he must clean up all harden overflow concrete and residual off of the hard surfaces as well. He responded to do so and will be building a preventative contaInment so if any overflow occur it will be contained on visquen with a sand bag barrier.
General Inspection1/28/20131/28/20131/28/2013 FAIL
DetailsClint A Smith
Verbal correction to RP;
Remove the washout bins full or over 50 percent full. Also clean up all residual that over flowed out of two of the bins. Will follow up on 1/31/2012.
General Inspection12/12/201212/12/201212/12/2012APASS
DetailsDave Hannah
Random Inspection12/5/201212/5/201212/5/2012PFAIL
DetailsClint A Smith
Verbal to RP:
protect the storm drain no the corner of 8th ST. and Main street. Will follow up on 12/6/2012 p.m.
General Inspection10/29/201210/29/201210/30/2012 PASS
DetailsClint A Smith
Both areas of the project are compliant. Daily clean up is occuring on the portion of the project at the tower. The staging area looks good as well.
Conference9/13/20129/13/20129/13/2012PDONE
DetailsClint A Smith
Discussed with the RP (Jamal) over the location of the washout containers at the staging area yesterday. Explained to him that they must be at a minimum of 50 ft from the exsisting storm drains. Also advised to him to eduxate to the concrete truck company that they must use the washouts correctly and try to avoid spillage outside of the washout containers.
General Inspection8/21/20128/21/20128/22/2012 PASS
DetailsKimberly M. Johnson
Staging area inspection conducted 8/21. 8th & Main inspection conducted 8/22
Site Preparation7/5/20127/5/20127/5/2012 PASS
DetailsClint A Smith