Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberESC12-00557
StatusFinaled
Name CHAD CANNON
Site Address 2708 E RHYOLITE CT
Project NameLasher Homes
Customer Number 
ePlanReviewNo
Description
Boulder Heights
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection10/30/201211/1/201211/2/2012APASS
DetailsClint A Smith
Site Final11/2/201211/2/201211/2/2012APASS
DetailsDave Hannah
DOC - Permit Finaled11/2/201211/2/201211/2/2012PPASS
DetailsDave Hannah
Random Inspection10/30/201210/30/201210/30/2012PFAIL
DetailsClint A Smith
verbal to rp;
clean up all sediment and debris off of the hard surfaces on a daily basis. also prior to the project being finaled, the access to the south east must be stabilized with approved methods.
General Inspection10/2/201210/2/201210/2/2012 PASS
DetailsClint A Smith
BMP Violation8/29/20128/29/20128/30/2012 PART
DetailsClint A Smith
Spoke with the RP over removing the washout and providing a new washout. Also the RP informed me that they will be placing in additional sediment control algong the perimeter of the project back behind walk.
BMP Violation8/22/20128/24/20128/27/2012APART
DetailsClint A Smith
Perimeter control fixed but still has trackout/sediment on road due to not using a stabilized access point to yard. Kiddie pool washout staged at edge of yard within 50 feet to storm drain and has holes in the bottom. All liquid was hardened. Washout pool needs to be disposed of ASAP. Left message for RP
General Inspection8/22/20128/22/20128/22/2012 FAIL
DetailsClint A Smith
C/N Message to RP:
Per BMC 8-17-2.1H & 8-17-2.4 N, your site is in violation. Corect by 8/23/2012PM.
1. Maintain all sediment controls along the perimeter.
2. Clean all sediment off of the hard surfaces from tracking.
Failure to comply with the notice will result in further enforcement. Will re-inspect on 8/24/2012AM.
Random Inspection7/18/20127/18/20127/18/2012PPART
DetailsMike Jordan
BMP Violation7/16/20127/17/20127/17/2012APART
DetailsClint A Smith
Verbal to RP:
Once the back fill has occured, relocate the washout container where it is not located by the storm water gutterpan.
BMP Violation7/13/20127/16/20127/16/2012AFAIL
DetailsClint A Smith
Correction Notice:
Install a sediment barrier along back of curb to prevent sedimentfrom leaving the project area.
Failure to comply will result in further enforcement. Will re-inspect on 7/17/2012.
Site Preparation7/13/20127/13/20127/13/2012 FAIL
DetailsClint A Smith
Verbal to Doug Lasher:
Provide sediment barrier along the back of curb. Relocate washout to a level area of the project where access is an ease. Will re-inspect on 7/16/2012