DOC - Permit Finaled | 4/21/2014 | 4/21/2014 | 4/21/2014 | P | PASS |
Andy J. Long
|
|
|
Finaled. See activity notes for details.
|
Site Final | 4/18/2014 | 4/21/2014 | 4/21/2014 | A | PASS |
Andy J. Long
|
|
|
Check to see if DI bag has been removed and gutter cleaned so ESC permit can be finaled.
DI bags have been removed as requested. ESC conditions satisfied. Landscaping to be completed by homeowner. Permit conditions satisfied.
|
General Inspection | 4/17/2014 | 4/18/2014 | 4/18/2014 | P | FAIL |
Andy J. Long
|
|
|
Need to remove temporary BMP (drop inlet protection in front of house for proper drainage) per ESC permit conditions. And clean some bark out of the gutter
|
General Inspection | 4/17/2014 | 4/17/2014 | 4/17/2014 | | CANC |
Andy J. Long
|
|
|
rescheduled for 4/18
|
General Inspection | 3/17/2014 | 3/17/2014 | 3/17/2014 | | PASS |
Evan Jenkins
|
|
|
work in progress no esc issues at time of inspection
|
General Inspection | 2/13/2014 | 2/13/2014 | 2/13/2014 | | PASS |
Andy J. Long
|
|
|
WIP. Contractors parking on completed driveway. House is nearly done, no landscaping/stabilization yet. Permit posted, no violations observed. Approved
|
General Inspection | 1/13/2014 | 1/13/2014 | 1/13/2014 | | PASS |
Evan Jenkins
|
|
|
No ESC Violations at time of inspection. Constructino sign posted onfront of house
|
General Inspection | 12/12/2013 | 12/12/2013 | 12/12/2013 | | PASS |
Andy J. Long
|
|
|
WIP. No track out or other violations observed.
|
General Inspection | 11/11/2013 | 11/11/2013 | 11/12/2013 | | CANC |
Evan Jenkins
|
|
|
Holiday
|
General Inspection | 10/10/2013 | 10/10/2013 | 10/10/2013 | | PASS |
Andy J. Long
|
|
|
No ESC corrections. WIP, no track out to 8th Street.
|
General Inspection | 9/9/2013 | 9/9/2013 | 9/16/2013 | | PASS |
Tony Young
|
|
|
|
General Inspection | 8/8/2013 | 8/8/2013 | 8/16/2013 | | PASS |
Tony Young
|
|
|
|
General Inspection | 7/8/2013 | 7/8/2013 | 7/8/2013 | | PASS |
Kimberly M. Johnson
|
|
|
|
General Inspection | 6/7/2013 | 6/7/2013 | 6/7/2013 | | PASS |
Clint A Smith
|
|
|
|
General Inspection | 5/7/2013 | 5/7/2013 | 5/7/2013 | | PASS |
Clint A Smith
|
|
|
|
BMP Violation | 4/3/2013 | 4/4/2013 | 4/4/2013 | P | PASS |
Kimberly M. Johnson
|
|
|
Stabilized entrance in and wattle re-installed. Will need to keep an eye on the small area of disturbance between curb and lot.
|
BMP Violation | 3/29/2013 | 4/3/2013 | 4/3/2013 | P | PART |
Kimberly M. Johnson
|
|
|
DI BMP cleaned and gutter swept although sediment has accumulated in front of wattle in gutter already. Still needs perimeter control along front of property and stabilized construction exit. Written correction notice issued.
|
Random Inspection | 3/29/2013 | 3/29/2013 | 3/29/2013 | P | FAIL |
Kimberly M. Johnson
|
|
|
Written correction notice issued: 1. sweep gutter. 2. clean DI bags. 3. Provide perimeter control along 8th. 4. provide stabilized access/exit.
|
Site Preparation | 2/28/2013 | 3/1/2013 | 3/1/2013 | A | PART |
Tony Young
|
|
|
more going on
|
BMP Violation | 2/19/2013 | 2/21/2013 | 2/22/2013 | A | PASS |
Eric Strole
|
|
|
|
BMP Violation | 2/14/2013 | 2/18/2013 | 2/19/2013 | A | FAIL |
Eric Strole
|
|
|
Left verbal and 2nd written correction that DI protection still needs to be installed and install wattles per manufacture installion. Need to be complete by 2-20-13 pm. Will reinspect on 2-21-13 am. If not complete a stop work may be issued.
|
Site Preparation | 2/14/2013 | 2/14/2013 | 2/14/2013 | P | FAIL |
Eric Strole
|
|
|
Left verbal correction via voice mail and a written correction to install sediment barriers along back of project and in front where entrance has been cut in and install DI protection. Needs to be complete by 2-15-13 PM. Will reinspect on 2-18-13 AM.
|
Site Preparation | 2/7/2013 | 2/7/2013 | 2/7/2013 | | NR |
Kimberly M. Johnson
|
|
|
|