Aging Inspection | 10/1/2013 | 10/1/2013 | 10/1/2013 | | PASS |
Andy J. Long
|
|
|
Finaled. See activity notes.
|
DOC - Permit Finaled | 10/1/2013 | 10/1/2013 | 10/1/2013 | P | PASS |
Andy J. Long
|
|
|
Construction complete. Site stabilized and landscaped. Looks occupied. Permit is finaled
|
Site Final | 4/1/2013 | 4/1/2013 | 4/1/2013 | P | NR |
Mike Jordan
|
|
|
final stabalization not completed.
|
General Inspection | 2/19/2013 | 2/19/2013 | 2/19/2013 | A | PART |
Mike Jordan
|
|
|
Sweep all silts from hard surfaces and put all construction debries in provided trash bin. Correction notice posted.
|
Random Inspection | 2/8/2013 | 2/8/2013 | 2/8/2013 | A | PASS |
Mike Jordan
|
|
|
|
BMP Violation | 2/4/2013 | 2/5/2013 | 2/6/2013 | P | PASS |
Clint A Smith
|
|
|
|
BMP Violation | 2/4/2013 | 2/4/2013 | 2/4/2013 | P | FAIL |
Clint A Smith
|
|
|
Correction notice Posted; (Verbal to RP) 1. Install sediment barrier along the east section of the project area. Re-install sediment barriers where installed incorrectly or delopidated on the south section of the project area. Will re-inspect on 2/5/2013 PM
|
BMP Violation | 2/1/2013 | 2/1/2013 | 2/4/2013 | P | FAIL |
Clint A Smith
|
|
|
Correction Notice;(verbal to RP and posted notice) 1. Protect the storm drain on the North West corner of the intersection. 2. Clean up all sediment and debris off of all the hard surfaces. 3. Install sediment barriers along the east and south perimeter of the project area. Also Re-install sediment barrier along the west side of the project area. Will re-inspect on 2/4/2013 PM
|
Site Preparation | 1/15/2013 | 1/15/2013 | 1/15/2013 | P | PART |
Mike Jordan
|
|
|
Rp on site installing BMP's.
|
Aging Inspection | 8/1/2013 | 8/1/2013 | | | |
Mike Jordan
|
|
|
|