Information based on query as of Friday, June 28, 2024.
Permit Information
Permit NumberESC13-00011
StatusFinaled
Name MICHAEL G COLE
Site Address 625 N 31ST ST
Project NameNew Regan Avenue Sewer Lift St
Customer Number 
ePlanReviewNo
Description
SITE PREPARATION INSPECTION MUST BE CALLED IN AND PASSED UPON COMPLETION OF ESC BMPS AND PRIOR TO EARTH MOVING ACTIVITIES DUE TO SENSITIVITY OF PROJECT
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection2/3/20142/3/20142/3/2014 DONE
DetailsEvan Jenkins
see final
DOC - Permit Finaled2/3/20142/3/20142/3/2014PPASS
DetailsEvan Jenkins
Talked w/ Mike Shapperd this past Friday about this project 1-31-14. He stated it is has been complete for some time now.
No ESC Issues
Complete
General Inspection1/17/20141/17/20141/17/2014 PASS
DetailsEvan Jenkins
No Activity at time of inspection
General Inspection1/2/20141/2/20141/2/2014 PASS
DetailsEvan Jenkins
No Activitiy at time of inspection, nor the previous 2 inspections
General Inspection12/18/201312/18/201312/18/2013 PASS
DetailsEvan Jenkins
General Inspection12/3/201312/3/201312/3/2013 PASS
DetailsEvan Jenkins
Track out occuring from the access road b/t the City's Lift Station and the Idaho River Sports Co. I suspect its from local people using it to get to the white water park/greenbelt. Talked with Alta Construction, they stated they been done working since october. Knife River has been finished since May. Contacted and left a VM to ACHD Jason Korn about the trackout.
General Inspection11/18/201311/18/201311/18/2013 PASS
DetailsAndy J. Long
Foundation is complete. Knife River is no longer on-site. Surrounding area is used as staging area for ALTA project. BLD permit is open - outstanding Electrical Permit fees due.

No ESC violations at this time.
General Inspection11/1/201311/1/201311/1/2013 PASS
DetailsAndy J. Long
Lift station and related infrastructure is installed. BLD permit is open Other phases of 31st/Whitewater Blvd project are ongoing. No stabilization yet. No violations at this time.
General Inspection10/17/201310/17/201310/17/2013 PASS
DetailsEvan Jenkins
General Inspection10/2/201310/2/201310/2/2013 PASS
DetailsAndy J. Long
WIP and site is not yet ready for stabilization. NO ESC violations at time of inspection. Dewatering and sewer infrastructure has been installed. Approved
General Inspection9/13/20139/13/20139/17/2013 CANC
DetailsDixie Fellows
cancel per bill
General Inspection9/16/20139/17/20139/17/2013ACANC
DetailsBill VanDegrift
bill, will you meet me at this site and check it over with me?? thanks dixie
General Inspection8/29/20138/29/20138/29/2013 PASS
DetailsDaryl Spivey
final stabilization not achieved yet.
General Inspection8/14/20138/14/20138/14/2013 CANC
DetailsKimberly M. Johnson
General Inspection7/30/20137/30/20137/31/2013 PART
DetailsKimberly M. Johnson
Waiting on stabilization
General Inspection7/12/20137/12/20137/12/2013 PART
DetailsClint A Smith
Need to achieve final stabiliztion
General Inspection6/27/20136/27/20136/27/2013 PASS
DetailsClint A Smith
General Inspection6/12/20136/12/20136/12/2013 CANC
DetailsKimberly M. Johnson
General Inspection5/24/20135/24/20135/24/2013 DONE
DetailsClint A Smith
Waiting on the deconstruction of the basin so stabilization measure can be implimented.
General Inspection5/9/20135/9/20135/9/2013 PART
DetailsClint A Smith
Need to break down basin and stabilize all portions of the disturbed soil.
General Inspection4/24/20134/24/20134/24/2013 PASS
DetailsClint A Smith
Site was visited yesterday. All ground water being pumped into the pond. By visual appearence, it look clean at the discharge point.
General Inspection4/9/20134/9/20134/9/2013PPART
DetailsClint A Smith
after establishing the discharge lines and discharge points into both the basin and pond, Knife River purged the well by pumping into the basin. At this time we took NTU measurements on the pond (background). the reading was 7.58 rounding up to 8 NTU's.
Giving them an allowable discharge of 58 NTU's.
At 3:25pm mountain standard time, the hard line discharge hose had a reading of 37 NTU's. The flexible line had a reading of 44 NTU's.
Knife River will now divert the hard line discharge to go directly into the pond. While they are estblishing there contections they will keep the flexible discharge line puming into the basin so a "purge" will not have to occur again. They will be pumping throught out the night. Once land disturbing activities begin in the morning all of the discharging will go directly into the basin with no discharges out into the pond.
General Inspection4/4/20134/4/20134/4/2013 DONE
DetailsClint A Smith
No activity
General Inspection3/20/20133/20/20133/20/2013 PASS
DetailsClint A Smith
No actiity until 3/8/2013
Conference2/27/20132/28/20132/28/2013PCANC
DetailsKimberly M. Johnson
PD scheduled meeting to discuss game plan. RP rescheduled for next week.
Random Inspection2/28/20132/28/20132/28/2013PPASS
DetailsKimberly M. Johnson
Dewatering of trench is complete. All water appears to have been retained on site in the retention basin and no discharges to the vegetated upland area occurred.
Random Inspection2/28/20132/28/20132/28/2013PPASS
DetailsKimberly M. Johnson
Dewatering of trench is complete. All water appears to have been retained on site in the retention basin and no discharges to the vegetated upland area occurred.
Random Inspection2/26/20132/26/20132/26/2013PPASS
DetailsClint A Smith
on 2/25/2013, Knife River reached ground water at 6.5ft. They stopped all activities with the utility pipe installation and began to impliment thier dewatering plan. Once completed with the detention basin and a well point, they will be calling for an inspection to review the dewatering activities.
Site Preparation2/26/20132/26/20132/26/2013PFAIL
DetailsKimberly M. Johnson
Met onsite with Mike Strasser (Boise PW), Keith (Knife River) and Clint Smith (Boise PDS). The anticipated pumping capacity exceeds the amount calculated for in the dewatering plan. This site is not approved to dewater to the neighboring surface water (un-named pond). Please submit a revised plan prior to discharging. Followed up with Mike Cole (Knife River) via telephone.
General Inspection2/21/20132/21/20132/24/2013PPASS
DetailsClint A Smith
ESC/ SWPPP approved. Explained to the RP to review the dewatering portion of the plan. It states, well point and drainage swale will be constructed prior to any dewatering from occuring. The plan states ground water is at a potental of 11ft below grade. Explained to RP if ground water is reached ant it is needed to dewater, The project must stop all activities and impliment the dewateering plan. Will follow up on 2/26/2013
Site Preparation2/14/20132/15/20132/18/2013PPART
DetailsClint A Smith
Only allowed to relocate stock pile. RP must have the "approved" ESC/ SWPPP plan for field verification before begining the next [hase of the project.
Site Preparation2/14/20132/14/20132/14/2013 CANC
DetailsClint A Smith
Moved to 2/15/2013