Aging Inspection | 4/14/2014 | 4/14/2014 | 4/14/2014 | | PASS |
Andy J. Long
|
|
|
Finaled.
|
DOC - Permit Finaled | 4/14/2014 | 4/14/2014 | 4/14/2014 | P | PASS |
Andy J. Long
|
|
|
Construction is complete and all materials removed. Yard is currently being landscaped by homeowner with dirt graded below sidewalk and curbing.
|
Aging Inspection | 2/11/2014 | 2/11/2014 | 2/11/2014 | | PASS |
Evan Jenkins
|
|
|
Work in Progress No ESC Issues at time of inspection
|
Aging Inspection | 12/10/2013 | 12/10/2013 | 12/10/2013 | | PASS |
Andy J. Long
|
|
|
WIP. Trash/demo materials containment bin in good condition. No materials on sidewalks or streets surrounding project. Approved.
|
Aging Inspection | 10/10/2013 | 10/10/2013 | 10/10/2013 | | PART |
Evan Jenkins
|
|
|
Active Construction Taking Place. Told RP verbally to Sweep sidewalk and keep all debris and sediment onsite (Off Sidewalk)
|
Site Preparation | 4/11/2013 | 4/11/2013 | 4/11/2013 | | PASS |
Rock A. Hudson
|
|
|
|