Aging Inspection | 8/11/2014 | 8/11/2014 | 8/11/2014 | | PASS |
Andy J. Long
|
|
|
Construction is complete, BLD permit finaled. Lanscaping and stabilization is installed. ESC permit conditions satisfied. Finaled.
|
DOC - Permit Finaled | 8/11/2014 | 8/11/2014 | 8/11/2014 | P | PASS |
Andy J. Long
|
|
|
|
Aging Inspection | 6/9/2014 | 6/9/2014 | 6/9/2014 | | PASS |
Andy J. Long
|
|
|
WIP. Mainly interior work remaining. Permit posted. No violations or sediment leaving site observed.
|
Aging Inspection | 4/7/2014 | 4/7/2014 | 4/7/2014 | | PASS |
Andy J. Long
|
|
|
Homeowner/contractor is RP. WIP. Front yard not yet stabilized. No violations observed.
|
Aging Inspection | 2/3/2014 | 2/3/2014 | 2/3/2014 | | PASS |
Andy J. Long
|
|
|
House construction is near completion. Yard is not yet landscaped. Wattles lining sidewalk. Approved.
|
Aging Inspection | 12/4/2013 | 12/4/2013 | 12/4/2013 | | PART |
Evan Jenkins
|
|
|
Left James King a VM describing to post the New Construction SIgn I left onsite and fill out all required information for contacts. Also to extend the gator guard all the to the north of the project to protect sediment leaving the site. I will reinspect in 48 hours to ensure compliance has bee met. When I was just leaving, James came out and talked with me about my VM. He stated he will do it right away
|
Aging Inspection | 10/3/2013 | 10/3/2013 | 10/3/2013 | | PASS |
Andy J. Long
|
|
|
Gatorguard perimeter BMP properly installed and consaining sediment. Permit posted. RP/builder is on site. Approved.
|
Site Preparation | 4/2/2013 | 4/2/2013 | 4/2/2013 | P | PART |
Clint A Smith
|
|
|
RP working on installing perimeter control on the ffront and the slope located on the back location.
|