Permit NumberESC13-00481
StatusFinaled
Name MICHAEL MC HARGUE
Site Address 10051 W SMOKE RANCH DR
Project NameUnion Square Apartments Phase
Customer Number 
ePlanReviewNo
Description
#14: Foundation Permit for Building #14
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled6/27/20146/27/20146/27/2014PPASS
DetailsAndy J. Long
General Inspection6/27/20146/27/20146/27/2014 PASS
DetailsAndy J. Long
Union Square Phase II is complete. No further construction. All disturbed areas landscaped and stabilized including the temporary staging area across Smoke Ranch. ESC conditions satisfied.
General Inspection5/9/20145/12/20145/12/2014APASS
DetailsAndy J. Long
BLD permit has been finaled. Some temporary BMPs are still in place as final landscaping is finishing up. Some construction materials still remain in the staging area as well. No trackout or other violations observed. Will check to see if any corrections/status on next general inspection.
General Inspection5/9/20145/9/20145/9/2014 CANC
DetailsAndy J. Long
rescheduled for Monday 5/12
General Inspection3/24/20143/24/20143/24/2014 PASS
DetailsEvan Jenkins
no esc issues at time of inspection
General Inspection2/4/20142/4/20142/4/2014 PASS
DetailsAndy J. Long
Road appears to be swept over weekend and construction entrance to staging area has new construction entrance. No corrections at this time. WIP.
Tracking Control12/20/201312/20/201312/20/2013PPEND
DetailsAndy J. Long
Follow up inspection from CN issued in the A.M.

Corrections complete:

1. Sidewalk on Goldking swept and stockpile materials removed with blow torches to unmelts, shovels to scrape
2. Street sweeper deiced and swept Goldking
3. Stockpile of sand relocated
4. Gyp-crete spill on Goldking cleaned

Corrections in progress:

1. Trash pick up on site
2. Designated concrete washout
General Inspection12/20/201312/20/201312/20/2013 PART
DetailsAndy J. Long
See ESC13-00482 for corrections on Union Square project. Clean up has been started.
General Inspection11/4/201311/4/201311/4/2013 PASS
DetailsAndy J. Long
BMPs have been maintained in response to correction order on other Union Square project. Construction entrances have been reparied, perimeter access fencing installed to restrict unauthorized entrance/track out. New DI bags placed on all inlets.
General Inspection9/18/20139/18/20139/24/2013 CANC
DetailsEvan Jenkins
General Inspection8/2/20138/2/20138/6/2013 CANC
DetailsKimberly M. Johnson
Site Preparation6/14/20136/14/20136/14/2013PPASS
DetailsKimberly M. Johnson
Construction access installation in process. No perimeter control required at this time per plan. RP to evaluate need during inspection. Inlet protection is in. Discussed soil type and extra precautions required for dust control, totes need to labeled. Discussed action items required to close out phase I permits. RP will issue permit modification for laydown yard on north side of smoke ranch drive