General Inspection | 2/23/2015 | 2/23/2015 | 2/23/2015 | | PASS |
Andy J. Long
|
|
|
Construction finished. Correction from previous inspection has been completed.
DI on Roosevelt still has inlet protection, but work is to resume on the swale which is owned by neighbor building to the north. Bag has remaining capacity so can remain in inlet.
ESC permit finaled.
|
DOC - Permit Finaled | 2/23/2015 | 2/23/2015 | 2/23/2015 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 12/22/2014 | 12/22/2014 | 12/22/2014 | | PART |
Andy J. Long
|
|
|
Jackson's remodel complete. BLD finaled. The drainage swale behind store is actually owned by neighbor, but Jackson's agreed to landscape it. Work was near completion before bad weather hit in November. RP Kenny provided update that the swale will be completed in the spring time when weather allows.
No sediment runoff leaving site. Swale drain does appear to be filled with mud.
Correction issued to Kenny: -shovel/sweep small pile of dirt on sidewalk into the swale - check in with ESC division when project is complete.
Kenny said he will make correction today and check on site.
|
DOC - Permit Finaled | 12/22/2014 | 12/22/2014 | 12/22/2014 | P | PASS |
Andy J. Long
|
|
|
(This activity was added in error so we have changed the case status back to Issued.)
|
Random Inspection | 10/20/2014 | 10/20/2014 | 10/20/2014 | A | PASS |
Andy J. Long
|
|
|
WIP at Jackson's remodel/addition. DI on Roosevelt has filter bag protection. No trackout and a lined concrete washout is on site. Permit posted. No violations observed.
|
General Inspection | 9/30/2014 | 9/30/2014 | 9/30/2014 | | PASS |
Andy J. Long
|
|
|
WIP on gutting old Jackson's store. No trenching or lineal work on hardscapes, the hole for the rear addition has been dug and stormwater flows inward to site. No corrections at this time.
|