Permit Information
Permit NumberESC13-00495
StatusFinaled
Name ADAM LYMAN
Site Address 2750 S PALMATIER WAY
Project NameHarris Ranch Community Center
Customer Number 
ePlanReviewNo
Description
Final Stabilization due Oct 2013 //(This permit to cover Bld13-01302 & Bld13-01332 ok per KMJ) 5/31/13 leg** Harris Ranch Community Center for Subdivision 7. Must complete final stabilization by Oct 2013 to maintain compliance with LEW
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection4/14/20144/14/20144/14/2014 PASS
DetailsAndy J. Long
Finaled.
DOC - Permit Finaled4/14/20144/14/20144/14/2014PPASS
DetailsAndy J. Long
Landscaping and vegetation surrounding Harris Ranch pool and community center satisfy ESC permit conditions. No futher construction activity and is operational.
General Inspection2/10/20142/10/20142/10/2014 PASS
DetailsAndy J. Long
No further construction activity. Some areas of community area that are hydroseeded have not grown in yet. No discharges from area. Will monitor for stabilization.
General Inspection12/10/201312/10/201312/10/2013 PASS
DetailsAndy J. Long
Stabilization in progress. No corrections at this time.
General Inspection10/9/201310/9/201310/9/2013 PART
DetailsEvan Jenkins
KJM placed notes saying "Final Stabilization will be established by October 2013".
Contractors are now building on the two parcels, and are approximately 40% complete.
Contacted Adam Lyman (RP) via cell phone to disclose this information and he stated he will contact me back after he finds out what is going on with progress.
General Inspection8/7/20138/7/20138/9/2013 PASS
DetailsDave Hannah
Site Preparation6/6/20136/6/20136/6/2013 NR
DetailsClint A Smith