General Inspection | 6/21/2016 | 6/21/2016 | 6/21/2016 | | DONE |
Evan Jenkins
|
|
|
|
DOC - Permit Finaled | 6/21/2016 | 6/21/2016 | 6/21/2016 | P | PASS |
Evan Jenkins
|
|
|
Over 80% re-vegetated. ESC Conditions Satisfied on this partifular lot.
|
General Inspection | 6/6/2016 | 6/6/2016 | 6/6/2016 | | PASS |
Evan Jenkins
|
|
|
Hillside SFH complete and occupied. Near 80% revegetated
|
General Inspection | 5/20/2016 | 5/20/2016 | 5/20/2016 | | PEND |
Evan Jenkins
|
|
|
|
General Inspection | 5/5/2016 | 5/5/2016 | 5/5/2016 | | PASS |
Evan Jenkins
|
|
|
SFH occupied and near 80% re-vegetated. No ESC issues observed
|
General Inspection | 4/20/2016 | 4/20/2016 | 4/20/2016 | | PEND |
Evan Jenkins
|
|
|
near 80% re-vegetated. No ESC issues at this time
|
General Inspection | 4/5/2016 | 4/5/2016 | 4/5/2016 | | PEND |
Evan Jenkins
|
|
|
|
General Inspection | 3/21/2016 | 3/21/2016 | 3/21/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 3/4/2016 | 3/4/2016 | 3/4/2016 | | PASS |
Evan Jenkins
|
|
|
minor interior activity occuring no esc issues
|
General Inspection | 2/18/2016 | 2/18/2016 | 2/19/2016 | | PEND |
Tony Young
|
|
|
|
General Inspection | 2/3/2016 | 2/3/2016 | 2/3/2016 | | PEND |
Evan Jenkins
|
|
|
|
General Inspection | 1/19/2016 | 1/19/2016 | 1/19/2016 | | PEND |
Evan Jenkins
|
|
|
re-vegetation
|
General Inspection | 1/4/2016 | 1/4/2016 | 1/4/2016 | | PEND |
Evan Jenkins
|
|
|
perm re-veg
|
General Inspection | 12/18/2015 | 12/18/2015 | 12/18/2015 | | PEND |
Evan Jenkins
|
|
|
|
General Inspection | 12/3/2015 | 12/3/2015 | 12/3/2015 | | PEND |
Evan Jenkins
|
|
|
|
General Inspection | 11/18/2015 | 11/18/2015 | 11/18/2015 | | PEND |
Evan Jenkins
|
|
|
80% Re-veg Grass is growing around perimeter of new drainage ditch and within the bottom of the trench. No ESC issues observed.
|
General Inspection | 11/3/2015 | 11/3/2015 | 11/3/2015 | | PASS |
Andy J. Long
|
|
|
BLD permit is finaled and hillside bond for stabilization/vegetation is in place. Downslope stormwater swale and berm are in good condition and is vegetating. Silt fence installed in areas where overflow could possbly occur. No corrections at this time. Will consider closing once house is close and inspect slope and swale under ESC13-00707 (1012 Braemere)
|
General Inspection | 10/19/2015 | 10/19/2015 | 10/19/2015 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 10/2/2015 | 10/2/2015 | 10/2/2015 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 9/17/2015 | 9/17/2015 | 9/17/2015 | | PASS |
Evan Jenkins
|
|
|
2 New Drains have been installed along with silt fence along the bottom drain, and straw waddle along the upper slope of newly dug drainage ditch. Rock check dam has also been installed with jute mate/erosion blanket.
|
Random Inspection | 9/2/2015 | 9/2/2015 | 9/2/2015 | P | PART |
Evan Jenkins
|
|
|
Inspection to see progress of new PW and ESC Requirements:
Two New drains have been installed, along with the birm dramatically increased in size to capture runoff. Remaining work: 1.) Install Wire Back Silt Fence below bottom drain in horseshoe shape, to capture any potential runnoff not entering bottom drain. 2.) Install Jute Mate in bottom of new catch basin (seed prior to installation of Jute Mat) 3.) Install Rip Rap around bottom drain for filtration.
|
General Inspection | 8/27/2015 | 8/27/2015 | 8/27/2015 | | FAIL |
Evan Jenkins
|
|
|
New Silt Fence still has not been installed as, I gave Bob Borrow and his crew several weeks ago during out onsite meeting with PW. Called Bob and left VM asking for an eta on installation and that he has 48hrs from now, or money from the his Bond will be pulled and I will hire another contractor to install the BMP's.
|
General Inspection | 8/12/2015 | 8/12/2015 | 8/12/2015 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 7/28/2015 | 7/28/2015 | 7/28/2015 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 7/13/2015 | 7/13/2015 | 7/13/2015 | | FAIL |
Evan Jenkins
|
|
|
Significant amount of sediment left the 4 lots, blowing out the silt fence along the bottom NW corner of the lot. Talked with RP Bob Borrow: He stated Jason Taylor is setting up a meeting with myself, Jason Taylor, Dean Briggs and Bob to discuss next options and how to correct these issues.
|
General Inspection | 6/26/2015 | 6/26/2015 | 6/26/2015 | | PEND |
Evan Jenkins
|
|
|
revegetation
|
General Inspection | 6/11/2015 | 6/11/2015 | 6/11/2015 | | PEND |
Evan Jenkins
|
|
|
perm vegetation re-establishment
|
Complaint Inspection | 5/27/2015 | 5/27/2015 | 5/27/2015 | P | PART |
Evan Jenkins
|
|
|
BMP's in place, but it appears that the significant rainstorm that came through last night overwhelmed some of the new grass that's growning. Also, the Rock Retaining walls on both homes are Eroding away (Not Constructed Correctly). Roof Drains are also causing issues. I contacted Bob to disclose the complaint and to place waddles along the hillside within the gully's to slow the velocity of precipitation. He stated he will be up this afternoon to rack out the gullys, place new seed and install waddles on all lots.
|
General Inspection | 5/25/2015 | 5/25/2015 | 5/26/2015 | | PEND |
Evan Jenkins
|
|
|
No activity, waiting for perm re-vegetation to be established
|
BMP Violation | 5/8/2015 | 5/8/2015 | 5/8/2015 | P | PASS |
Andy J. Long
|
|
|
check that silt fence has been repaired. Builder called to say he made corrections in the AM in response to yesterday's inspection.
Silt fence breech has been fixed with new fencing. The drainage swale that overflowed was increased in size and the berms walls raised and some rock installed. Builder talked to neighbor with sediment coming on to property and has resolved the issue.
This is only a temporary fix. Slope still need to be hydroseeded and a solution to the irrigation runoff issue needs to be found.
|
Complaint Inspection | 5/7/2015 | 5/7/2015 | 5/7/2015 | P | FAIL |
Andy J. Long
|
|
|
Collective runoff from irrigation of both 970 & 1012 Braemere is concentrating and creating a gully that has under cut the silt fence with sediment leaving site and beginning to enter neighbors yard.
Correction: 1. Decrease water to 1-2x times a week. Barrow contruction contact David stated this frequency was decreased last week. 2. Need to install check dams along channel that has formed and extend the diversion channel to carry water further down from the existing channel.
3. Install addition sediment control below silt fence breach and repair gully that has formed.
4. Rake/clean up deposited sediment on adjacent property back into lot behind silt fence.
Noted - it was disclosed that a hydroseeding contractor is to come the week of 5/10-5/15
|
General Inspection | 4/29/2015 | 4/29/2015 | 4/29/2015 | | PASS |
Evan Jenkins
|
|
|
No changes to the site. perm re-vegetation still needs to be established
|
General Inspection | 4/14/2015 | 4/14/2015 | 4/14/2015 | | PEND |
Andy J. Long
|
|
|
No changes or activity at site. No corrections at this time. Both homes still need to pass hillside grading and roof top stormwater drainage and remaining disturbed areas need hydroseeding/final stabilization
|
General Inspection | 3/30/2015 | 3/30/2015 | 3/30/2015 | | PART |
Andy J. Long
|
|
|
Home construction complete, home is for sale and is landscaped but is not occupied. No activity. Bottum hillside is still establishing vegetation cover, which is why permit is open
Some minor rill erosion has occured on lower portion of yard due to irrigation water runoff from the sod area. Grading has been tracked horizontally and the silt fence BMP is containing sediment onsite and is properly installed. Site has been swept and materials cleaned.
Correction: Rake out rills and reseed/stabilize as necessary
|
General Inspection | 3/13/2015 | 3/13/2015 | 3/13/2015 | | PASS |
Evan Jenkins
|
|
|
No activity at this time waiting for perminant stabilization
|
General Inspection | 2/26/2015 | 2/26/2015 | 2/26/2015 | | PASS |
Evan Jenkins
|
|
|
down hill of home has been prepped for hydroseed
|
General Inspection | 2/11/2015 | 2/11/2015 | 2/11/2015 | | PASS |
Evan Jenkins
|
|
|
Silt fence below home has been fixed. Waiting for final stablization to take place.
|
General Inspection | 1/27/2015 | 1/27/2015 | 1/27/2015 | | PASS |
Evan Jenkins
|
|
|
Final stabilization needs to be established. No activity at time of inspection
|
General Inspection | 1/12/2015 | 1/12/2015 | 1/12/2015 | | PASS |
Andy J. Long
|
|
|
1 of 4 Barrow sub homes. BLD is open, though no new exterior work. Slope below yard needs further stabilization/hydroseeding
|
General Inspection | 12/26/2014 | 12/26/2014 | 12/26/2014 | | PEND |
Andy J. Long
|
|
|
still need to fix hillside drainage. Silt fence still installed and buffer in place.
|
BMP Violation | 12/11/2014 | 12/11/2014 | 12/11/2014 | A | FAIL |
Evan Jenkins
|
|
|
Complaint Inspection Silt Fence needs to be replaced along entire bottom of all the sites, debris pile to be removed and sidewalks swept. Superintendent stated on phone to me he will have the silt fence fixed within a couple hours and debris pile removed today or tomorrow morning. I will follow up this afternoon to ensure silt fence has been repaired
|
Conference | 12/2/2014 | 12/3/2014 | 12/3/2014 | A | PEND |
Andy J. Long
|
|
|
Call contractor to discuss hillside erosion that is occuring at site.
Discussed drainage and erosion issue at site with GC Bob. Plan is to regrade the area below the existing landscaping while also addressing rooftop stormwater drainage system issues. BLD permit is open pending final and Public Works drainage inspection.
Excavator is onsite currently but conditions are still very muddy and not good for work. Landscapers are to be onsite later this week to assist in the work. Currently the loose sediment in the runoff is being contained by the silt fence, but the issue needs to be fixed ASAP when conditions allow.
As an immediate fix I recommended installing some check dams in the rill to start filling it in.
Bob is to keep me posted on corrective actions.
|
General Inspection | 12/2/2014 | 12/2/2014 | 12/2/2014 | | PART |
Andy J. Long
|
|
|
No further construction activity, home is occupied; permit open for hillside stabilzation/vegetation requirement.
The drainage channel is directing too much water to one section of hillside causing significant rill erosion that could worsen with time and more runoff. Loose sediment is currently being trapped by the silt fence installed and the vegetative buffer that was preserved at bottom of Barrow sub.
Correction: - grade out rills, fix/re-route drainage channel - do maintenance on several sections of silt fence.
T
|
General Inspection | 11/17/2014 | 11/17/2014 | 11/17/2014 | | PASS |
Andy J. Long
|
|
|
Construction complete, but will remain open until it is clear the downslope vegetation is growing and the roof drainage isn't causing erosion of hillside. No activity at site, no corrections at this time.
|
General Inspection | 10/31/2014 | 10/31/2014 | 10/31/2014 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 10/16/2014 | 10/16/2014 | 10/16/2014 | | PASS |
Evan Jenkins
|
|
|
BMP's still in place. waiting for re-vegetation to establish
|
General Inspection | 9/15/2014 | 9/15/2014 | 9/15/2014 | | PEND |
Andy J. Long
|
|
|
Home is near completion with landscaping, sod placement and retaining walls complete. BLD permit is still open.
The area between yard and downslope silt fence will have rills raked out and the area hydroseeded.
Silt fence will stay installed until slope stabilization. Will continue to monitor. No significant trackout or issues on street.
|
General Inspection | 8/14/2014 | 8/14/2014 | 8/14/2014 | | PASS |
Andy J. Long
|
|
|
Downslope silt fences are installed and trenched in. Currently in good shape. No landscaping or stabilzation on back yard, though no erosion observed. Permits posted.
|
General Inspection | 7/14/2014 | 7/14/2014 | 7/14/2014 | | PASS |
Evan Jenkins
|
|
|
no esc issues at time of inspection work in progress
|
General Inspection | 6/12/2014 | 6/12/2014 | 6/12/2014 | | PASS |
Evan Jenkins
|
|
|
New Silt fence has been installed per correction notice posted during last inspection. No ESC Issues at time of inspection
|
Complaint Inspection | 5/12/2014 | 5/12/2014 | 5/12/2014 | A | FAIL |
Evan Jenkins
|
|
|
Contractor has 48 hrs to Install down gradient Silt Fence BMP along entire bottom portion of disturbed lots. If not Acheived, a STOP WORK ORDER WILL BE ISSUED ON ALL LOTS that are out of compliance via 8-17 Boise City ESC Ordinance
|
General Inspection | 5/6/2014 | 5/6/2014 | 5/6/2014 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 4/3/2014 | 4/3/2014 | 4/3/2014 | | PASS |
Andy J. Long
|
|
|
Permit posted, no trackout, and sidewalks are clean. Work at bottom of site is staying within clearing limits. Vegetative barrier beyond the limits.
|
General Inspection | 3/3/2014 | 3/3/2014 | 3/3/2014 | | PART |
Evan Jenkins
|
|
|
Silt fence along bottom of site still needs repaired/maintained/replaced. Sidwalks & curbs have been swept
|
General Inspection | 1/31/2014 | 1/31/2014 | 1/31/2014 | | FAIL |
Evan Jenkins
|
|
|
Sediment leaving the site throughout the project, onto ACHD's sidewalk, curb and Right-of-Way. Attempted to call RP Bob Borrow via cell and left a voicemail describing the violations. Also, there is no Construction sign posted on any of the houses/projects taking place, which I described to him also they need to be posted. Andy placed notes a month ago that the RP is to Re-post Construction Signage, in which RP has not done to date. RP to Sweep sediment off sidewalk, curb and ROW back onto the site asap and also post construction signage
|
General Inspection | 12/31/2013 | 12/31/2013 | 12/31/2013 | | PART |
Andy J. Long
|
|
|
BMPs installed and downslope silt fence is in good condition. No ESC violations other than permit is not visible from road. RP will repost.
|
General Inspection | 11/27/2013 | 11/27/2013 | 11/27/2013 | | PART |
Evan Jenkins
|
|
|
Talked with RP onsite to sweep sidewalk prior to leaving site today. He stated he "Gets It" and will
|
General Inspection | 10/23/2013 | 10/23/2013 | 10/23/2013 | | PASS |
Andy J. Long
|
|
|
Downslope silt fence is installed. Minimal trackout. WIP.
|
General Inspection | 9/19/2013 | 9/19/2013 | 9/20/2013 | | PART |
Bill VanDegrift
|
|
|
talked to rp about cleaning up concrete and providing a washout pit at the next pour
|
Site Preparation | 8/6/2013 | 8/7/2013 | 8/7/2013 | A | PASS |
Kimberly M. Johnson
|
|
|
Bob Phone #: ###-####
|
Site Preparation | 8/6/2013 | 8/6/2013 | 8/6/2013 | P | FAIL |
Kimberly M. Johnson
|
|
|
Spoke to RP about requirements. Will get site ready and will schedule inspection tomorrow AM
|
Site Preparation | 8/2/2013 | 8/5/2013 | 8/5/2013 | A | FAIL |
Kimberly M. Johnson
|
|
|
KEITH Phone #: ###-####. Called to ask where plans are. Keith is on his way to site with plans. Waited around for 45 minutes. Reschedule site prep inspection when plans are on site
|