General Inspection | 5/9/2014 | 5/9/2014 | 5/9/2014 | | DONE |
Evan Jenkins
|
|
|
see final
|
DOC - Permit Finaled | 5/9/2014 | 5/9/2014 | 5/9/2014 | P | PASS |
Evan Jenkins
|
|
|
Complete BMP's pulled finished
|
General Inspection | 3/24/2014 | 3/24/2014 | 3/24/2014 | | PASS |
Evan Jenkins
|
|
|
no esc issues at time of inspection
|
Random Inspection | 2/5/2014 | 2/5/2014 | 2/5/2014 | A | PASS |
Andy J. Long
|
|
|
Observed that Jackson's on State is open but permit is open. BLD permit has temp occupancy, will keep open until all landscaping is complete. Onsite stormdrain at northwest corner has still have filter bag installed. Port-a-pot still onsite.
|
General Inspection | 1/14/2014 | 1/14/2014 | 1/14/2014 | | PASS |
Evan Jenkins
|
|
|
|
BMP Violation | 11/26/2013 | 11/26/2013 | 11/26/2013 | P | PART |
Andy J. Long
|
|
|
Street and main areas of trackout on 31st Street were swept manually. Street sweeper to come after 5 PM due to traffic and parking concerns per contractor Mike. Will reinspect following morning when in the area. Main corrections have been addressed and conditions have been improved.
|
General Inspection | 11/26/2013 | 11/26/2013 | 11/26/2013 | P | FAIL |
Andy J. Long
|
|
|
DEQ complaint DEQ Complaint: Excessive Tracking. Correction Notice Posted; Andy will reinspect today 11-26-13 at 4pm. Contractor to sweep all roads in vacinity, along with sidewalks and curbs. If not completed by 4pm today, a Stop Work Order WILL be issued
|
General Inspection | 11/13/2013 | 11/13/2013 | 11/13/2013 | | PART |
Evan Jenkins
|
|
|
Entrance located near 31st & State St. needs either blocked, or construction entrance installed to reduce trackout onto 31st st.
|
General Inspection | 9/24/2013 | 9/24/2013 | 9/24/2013 | | CANC |
Andy J. Long
|
|
|
duplicate entry, inspection completed by EEJ
|
Site Preparation | 9/24/2013 | 9/24/2013 | 9/24/2013 | P | FAIL |
Evan Jenkins
|
|
|
mike Phone #: ###-#### Contractor to Post Construction Sign, Install Perimeter BMP's and Construction Entrance. Will Re-Inspect once contractor calls for another walk through. EEJ
|
Site Preparation | 9/25/2013 | 9/25/2013 | | P | |
|
|
|
|