General Inspection | 4/4/2014 | 4/4/2014 | 4/4/2014 | | PASS |
Andy J. Long
|
|
|
Finaled.
|
DOC - Permit Finaled | 4/4/2014 | 4/4/2014 | 4/4/2014 | P | PASS |
Andy J. Long
|
|
|
Expansion has been complete, some vertical construction is remaining. The grading and grubbing phase under this permit is complete. ESC13-00650 covers south warehouse, and ESC13-00277 for north side office expansion are still open. No violations.
|
General Inspection | 2/17/2014 | 2/17/2014 | 2/17/2014 | | CANC |
Evan Jenkins
|
|
|
holiday
|
General Inspection | 12/31/2013 | 12/31/2013 | 12/31/2013 | | PASS |
Andy J. Long
|
|
|
Stabilization in progress. Stockpiles still in use for landscaping. No corrections at this time.
|
General Inspection | 11/14/2013 | 11/14/2013 | 11/14/2013 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 9/27/2013 | 9/27/2013 | 9/27/2013 | | PASS |
Andy J. Long
|
|
|
|