DOC - Permit Finaled | 5/20/2014 | 5/20/2014 | 5/20/2014 | P | PASS |
Andy J. Long
|
|
|
Constrtuction is complete. Melanie from K2 called to explain the stabilization plans for the narrow strip of disturbed land to the NW of the site. It has had gravel in areas and also seeding. ESC conditions satisfied. No corrections or further actions necessary.
|
General Inspection | 4/28/2014 | 4/28/2014 | 4/28/2014 | | PEND |
Andy J. Long
|
|
|
Need to wait for stabilization/vegetation along NW property line. Spoke with RP Melanie who will find out if the stabilization is part of the project. She will call after discussing with the project manager.
|
General Inspection | 3/11/2014 | 3/12/2014 | 3/12/2014 | A | PASS |
Andy J. Long
|
|
|
rescheduled from 3/11
No trackout to Federal Way. Parking lot and access has now been paved with asphalt. Will need to do some final materials removal before Final. No corrections at this time.
|
General Inspection | 3/11/2014 | 3/11/2014 | 3/11/2014 | | CANC |
Andy J. Long
|
|
|
rescheduled for 3/12
|
General Inspection | 1/22/2014 | 1/22/2014 | 1/22/2014 | | PASS |
Evan Jenkins
|
|
|
Site covered in snow, cannot see any violations at time of inspection
|
General Inspection | 12/4/2013 | 12/4/2013 | 12/4/2013 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 10/17/2013 | 10/17/2013 | 10/17/2013 | | PASS |
Evan Jenkins
|
|
|
|