Permit Information
Permit NumberESC13-00755
StatusFinaled
Name PRESTON ELLINGFORD
Site Address 5301 E WARM SPRINGS AVE
Project NameThe Terraces of Boise
Customer Number 
ePlanReviewNo
Description
This Permit does not cover the laydown yard, see ESC13-00793. The project will consist of the construction of a continuing care retirement community campus consisting of 138 independent apartments, 3 future guest apartments, 12 country home (6 duplexes), 40 assisted living units, 24 memory support suites, and 3-16 bed skilled nursing cottages.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final3/21/20163/21/20163/21/2016PPASS
DetailsAndy J. Long
All temporary BMPs are now removed around the Terraces site as requested. All disturbed area stabilized.

Permit conditions satisfied. All ESC permits associated with the Terrances are now finaled out. Notified RP Preston.
General Inspection3/15/20163/15/20163/15/2016 CANC
DetailsAndy J. Long
General Inspection2/29/20162/29/20162/29/2016 PART
DetailsAndy J. Long
Still cannot final out permit due to two temp DI bags still installed and full of muck on Council Springs. Called Preston with Ada Sand & Gravel to remove the bags.

He stated he will make sure it is done this week and will call to notify me. Construction is complete at Terraces and this is the only remaining item to satisfy permit conditions.
General Inspection2/12/20162/12/20162/12/2016 PEND
DetailsAndy J. Long
Request issued to remove 2x DI bags south of the west entrance to the Terrances on Council Springs Rd.

JC with Petra stated he have them removed. This is final step needed to close the permit.
Site Final1/28/20161/28/20161/28/2016PNR
DetailsAndy J. Long
Need to remove DI bags on Council Springs near the west entrance to Terrances.
General Inspection1/28/20161/28/20161/28/2016 CANC
DetailsAndy J. Long
rescheduled for site final. RP stated all temp BMPs are removed around the Terraces.
General Inspection1/13/20161/13/20161/13/2016 PASS
DetailsAndy J. Long
No activity at Terraces. Some equipment is still in the laydown and some final clean up needed.

Some temp BMPs have been removed, will do final walk-through next general inspection.
General Inspection12/29/201512/29/201512/29/2015 PASS
DetailsAndy J. Long
Minimal activity on the interior. Staging area is almost clear of construction items. Will check DI bag installations next general inspection. No violations at site.
General Inspection12/14/201512/14/201512/14/2015 PASS
DetailsAndy J. Long
WIP on interior on east buildings. No earthwork occuring. All landscaping is complete and disturbed areas are stabile. Laydown yard is still in use and is permitted seperately. DI bags still installed. No discharges or violations observed. Approved.
General Inspection11/27/201511/27/201511/27/2015 CANC
DetailsAndy J. Long
No earth disturbing work at this time. Project scheduled to be completed by end of December. No inspection conducted at this time.
General Inspection11/12/201511/12/201511/12/2015 PASS
DetailsAndy J. Long
Terraces project is near completion with plans to be done in December. Staging area is still in use, no trackout from entrance. East entrance off Lysted is now paved and landscaped and SWPPP information posted clearly. No discharges or trackout. No corrections at this time, no DI bags have been removed yet from site, RP stated they will all be pulled at once after final stabilization of all disturbed areas and removal of materials.
General Inspection10/28/201510/28/201510/28/2015 PART
DetailsEvan Jenkins
Trackout occuring within the interior of the site, but not leaving the project. Project near complete. no other issues observed at this time
General Inspection10/13/201510/13/201510/13/2015 PASS
DetailsAndy J. Long
WIP. Phase I is fully complete and reportedly 80% occupied. Nearly all grounds are landscaped and in the process of being cleaned.

RP JC informed me that laydown yard deactivation and completion of project is scheduled for Dec. 1st.

Syman Co. has been ordered by Ada Sand & Gravel/Petra to pull all DIs in phase I asap as it is stabilized and do not want to cause drainage issues with Fall leaves.

Approved. No violations observed, no complaints or issues received.
General Inspection9/28/20159/28/20159/28/2015 PASS
DetailsAndy J. Long
Terraces construction is still in progress with interior work on the east building as well as lanscaping. Minor amount of trackout from laydown yard due to construction entrace and Lysted street has recently been swept.

DI bags installed until all areas stabilized; no fugitive litter or dust from site. No corrections at this time.
General Inspection9/11/20159/11/20159/11/2015 PASS
DetailsAndy J. Long
WIP on northeast corner of complex. Construction work and landscaping occuring simultaneiously. All DI bags are still installed, but will all need to be pulled once the project is fully complete.

No trackout or discharges, the Terraces is over 60% complete. Construction entrance into laydown yard is in good condition. No corrections at this time. Will contact Petra next inspection to check on DI bags in stabilized areas around Council Springs entrance.
General Inspection8/27/20158/27/20158/27/2015 PASS
DetailsAndy J. Long
The west end of the Terraces is landscaped, paved and construction is complete. Residents are already living in the condo units and some of the hospital building.

Construction is remaing along the east end of site. All construction traffic is using the east entrance off Lysted. No significant trackout from site or laydown yard.

All DI bags are installed around the perimeter, so will need to make sure Petra removes them when complete with disturbed areas.
General Inspection8/12/20158/12/20158/12/2015 PASS
DetailsAndy J. Long
Terraces is still in progress. Most work is on the east end of the project. The condo units are complete, landscaped and many are occupied.

Silt fence lining southern boundary was removed and a permanent stormwater control (rocky swale) has been installed and surrounding area landscaped.

No trackout, gutters around site are free of significant amounts of trackout. No corrections issued, site is in good condition currently.
General Inspection7/28/20157/28/20157/28/2015 PASS
DetailsEvan Jenkins
WIP: Structurally and also landscaping for perm re-vegetation of previously disturbed areas.
No ESC violations observed
General Inspection7/13/20157/13/20157/13/2015 PASS
DetailsAndy J. Long
No trackout or discharges from Terraces site observed. Streets and gutter free of significant amounts of sediment and DI bags are installed. The silt fence will soon be removed as landscaping is completed behind the condo units. No blowouts to alley way occuring.

No corrections at this time.
General Inspection6/26/20156/26/20156/26/2015 PASS
DetailsAndy J. Long
Terraces is in good condition. No fugitive dust from vehicle traffic or construction. No discharges or trackout around perimeter. Materials are contained. No complaints received yet this summer from surrounding residents. Approved.
General Inspection6/11/20156/11/20156/11/2015 PASS
DetailsEvan Jenkins
Majority of buildings have been landscaped, with some minor trackout onto lazazio
General Inspection5/27/20155/27/20155/27/2015 PASS
DetailsEvan Jenkins
WIP:
landscaping is occuring around completed buildings and stormwater retention ponds. No trackout leaving the site at this time
General Inspection5/12/20155/12/20155/12/2015 PART
DetailsAndy J. Long
Terraces perimeter BMPs (south border silt fence and DI bags) are installed keeping sediment on site and out of storm drains. The condos have now been landscaped. Need to determine what will occur when silt fence is removed.

The main access drive is now paved from Council Springs to Lysted. A temporary construction entrance was installed on Warm Springs for work on the north side of site. Landscaping is occuring in different phases.

Overall site is in good condition with no discharges, no fugitvie dust or other erosion issues, but some corrections are needed:

1. Improve construction entrance on Warm Springs with larger rock and longer distance as possible.
2. Sweep up trackout on Warm Springs
3. Clean up/shovel mud accumulations in gutter on access road at the Council Springs entrance.
General Inspection4/27/20154/27/20154/27/2015 PASS
DetailsAndy J. Long
Terraces site perimeter recently swept by ACHD trucks. Warm Springs, Council Springs, and Lysted are in good condition.

East site exit is being preped for paving. Recieving inlets have DI filter bags installed. Silt fence along southern project boundary has silt fence installed and should remain so until bank behind condos is stabilized and irrigation isn't causing rills.

No dust issues observed or complaints received. No spills or trackout
General Inspection4/10/20154/10/20154/10/2015 PASS
DetailsAndy J. Long
No significant trackout from Terraces. Interior of site has considerably less loose dirt on paved surfaces due to periodic sweeeping efforts.

All receiving storm drains have drop inlet sediment protection. Parking lot for employes is still stabilized with rock mix. No fugitive dust observed at site, water truck on site to wet down roads/traffic areas through site.

No corrections requested at this time.
General Inspection3/26/20153/26/20153/26/2015 PASS
DetailsAndy J. Long
No significant trackout from either entrance to Terraces. Surrounding streets and gutters have been recently swept. No corrections at this time. WIP>.
Tracking Control3/11/20153/11/20153/11/2015PPASS
DetailsAndy J. Long
Returned by Terraces site to see if corrections and clean up were completed on Lysted, which was dirty due to trackout from east construction entrance.

At time of inspection, the sweeper unit had passed over the street and workers were push brooming and shoveling up the dirt that was left behind. Street looks much better and amound of sediment in gutter has been significantly reduced. Receiving inlet has DI filter bag with capacity.

No other areas of new trackout observed
Random Inspection3/10/20153/10/20153/10/2015PPART
DetailsAndy J. Long
Requested that Lysted Street south of construction entrance receive special sweeping attention today during the on-site sweeper rounds. It appears it has not been swept since last week, or new dirt is tracked out each day.

Petra supervisor JC stated that this afernoon it will be taken care off. Rain is forecasted for tomorrow.

Rest of site is in good condtion with no major trackout or loose sediment areas.
General Inspection3/5/20153/5/20153/5/2015 PART
DetailsAndy J. Long
Terraces perimeter BMPs (silt fence and DI bags on MS4) are installed and in good condition. No trackout from stabilized west parking lot, staging area, or on Council Springs.

The west side of Lysted Street needs sweeping and the east construction access continues to be a source of trackout and loose sediment.
General Inspection2/18/20152/18/20152/23/2015 PASS
DetailsAndy J. Long
Terraces silt fence perimeter and DI protection BMPs are in good condition.

There is some trackout on Council Springs and Lysted, but inspection has been performed prior to daily cleanup. No significant accumulations, mud clods or discharges. Will check road conditions through out week but appears Warm Springs has been recently cleaned.

No corrections at this time.
Conference2/3/20152/3/20152/3/2015PDONE
DetailsAndy J. Long
Site SWPPP coordinator JC from Petra called regarding some ESC issues at the Terraces.

Problems include trackout and offsite muddy runoff to surrounding gutters and storm drains.

Corrective actions are to check that DI bags are working and have capacity, add gutter bags in gutters at west entrances to stop sediment before it leaves site.

Cleaning up mud in gutters with shovels and street sweeping is also scheduled to occur, but the rain has been impeding progress.

I requested that corrective actions be documented in SWPPP file.
Tracking Control1/28/20151/28/20151/28/2015APEND
DetailsAndy J. Long
Corrections not yet complete. Weather conditions making sweeping difficult.

Street shoulders are still very dirty and do not appear thoroughly swept. Construction entrances have not yet be repaired/turned over. Some sweeping did occur however as stated. New mud clod trackout from laydown yard (due to entrance conditions) through neighborhood to Council Springs entrance also needs cleaning.

Will check back. Extremely muddy and difficult conditions. Storm drains do filter bag protection but no sheet flow runoff occuring currently.
Tracking Control1/27/20151/27/20151/27/2015PFAIL
DetailsAndy J. Long
Significant trackout onto Council Springs and extending west on Warm Springs. Paved access road through Terraces is also very muddy.

Corrections:
1. Sweep up trackout on Council Springs, Warm Springs and roundabout on Lysted.
2. Scarify or add more rock to the laydown yard construction entrance.
3. Re-implement adminstrative controls within site in regards to delivery and material unloading to reduce trackout.
Random Inspection1/16/20151/16/20151/16/2015PPASS
DetailsAndy J. Long
Terraces took good precautions to prevent trackout and sediment runoff today with the rain. No muddy discharges to storm drains or trackout observed.
Precautions taken:

1. East gate was locked to prevent trackout to Lysted.
2. Limited vehicle traffic to hard surfaces only
3. Employee parking areas have been resurfaced with rock and gravel to prevent trackout and creation of large mud puddles.

No corrections needed
Random Inspection1/6/20151/6/20151/6/2015PPASS
DetailsAndy J. Long
Streets surrounding Terraces are in decent condition with the central road relatively free of mud - indicating improvements in managing workers and materials to avoid/minimize trackout.

Silt fence BMP and drop inlet protection is in place. No corrections at this time.
Random Inspection12/24/201412/24/201412/24/2014APART
DetailsAndy J. Long
Parking lots in staging area and west side parking lot have been cleaned up and have rock base installed to keep mud down. Much improved. Silt fence and DI protection in good condition.

Significant amount of loose sediment on Council Springs and surrounding area so still getting a lot of trackout of sediment from the the west entrance to Terraces.

Sweeper was onsite, but site still needs to continue to make changes to prevent trackout.
General Inspection12/17/201412/17/201412/17/2014PPASS
DetailsAndy J. Long
Follow up inspection to check on conditions at site and corrections from last week's meeting.

Corrections completed:
1. Damaged silt fence sections have been repaired and dirt in alley way from the breach swept up.
2. Drop inlet bags were checked and maintained
3. Trackout from loading vehicles has been swept up and it appears that daily sweeping is occuring (noticed dirt from Tuesday was cleaned up on Wednesday)

Need to continue implementing administrative changes to prevent trackout and do the best to keep workers and vehicles off muddy areas within the site. Need to move employee parking to laydown yard to improve trackout situation at Council Springs.

Site in much better condition now and corrective actions have been made. Daily housekeeping and vigilance must continue due to the large complex operation.

Will continue to monitor improvement.
Conference12/11/201412/11/201412/11/2014PPASS
DetailsAndy J. Long
Site meeting requested to discuss CN issued 12/10. Petra, Idaho Sand & Gravel, Syman Co, and City of Boise ESC division will be in attendance

Meeting summary:

Correctiive actions already completed/in progress:
1. Sweeper with vacuum swept the perimeter roadways and removed loose sediment that had accumulated on Warm Springs.
2. Crew has started cleanup of dirt/mud in gutters.

Meeting summary & conclusions:
1. Material delivery will be restricted to mornings before 10 AM. The idea is that during winter, the morning may still have frozen ground. Also, after 10 AM the east construction access will be closed so that any clean up of trackout need can be completed only once that day without fear that more trackout will be caused by next delivery.
2. Designate a clean/mud free forklift or material hauler to ferry materials from laydown yard to main site. Muddy forklifts should not leave the main site.
3. Syman Company was at meeting and will be maintaining all drop inlet bags and the section(s) of damaged silt fence. Syman Co. is handling SWPPP inspections every 2 weeks and after rain events. There is a process in place for Petra to review and respond to inspection findings/deficiencies. Syman may consider switching to weekly inspections.
4. Employee parking is to be moved to the laydown yard where there is a good gravel & rock base. Until this time, the sweeper will be cleaning the parking lot exit.
5. Pit run access roads have been installed on site by Idaho Sand & Gravel. Worker training, signage, and installing fencing or caution tape to keep vehicles on these roads and out of the mud will cut down on dirt on hard surfaces.

Site conditions have improved since yesterday. All representative at meeting were in agreement on the plan for corrective actions.

Will continue to monitor and check progress.
Complaint Inspection12/10/201412/10/201412/10/2014PFAIL
DetailsAndy J. Long
Inpsection conducted at 1:00 pm

Observations:
-Trackout from employee parking area to the west of site (across Council Springs). Mud on employee cars is contributing to the dirty streets.
- Construction entrace on Lysted has caked in with mud, resulting in trackout.
- Sections of perimeter silt fence and construction fencing are damaged and need repair.
- Sediment and mud in gutters is not being picked up by the sweeper unit that is on site. Council Springs in particular.

Note: due to the vertical construction and large scale of the project there is a lot of heavy machinery, supplies, loading/unloading trucks, and workers within the site. Space for designated parking and storage is very limited and the mud hasn't been able to dry, creating a tough situation to manage. Interior can be muddy, but need to make sure that offsite trackout is controlled and prevent discharges of muddy water.

Corrections:
1. Continue sweeping all surrounding streets and the paved access road within site.
2. Restore construction entrance (Lysted & parking area)
3. Clean gutters on Council Springs
4. Repair damaged sections of silt fence and sweep alley in areas where dirt has migrated.

Site supervisor JC with Petra stated that sweeping has been occuring daily, he is restricting access to the east construction entrance when muddy, and they have been scraping the central access road occassionally.

Need to continue these efforts and have a specific crew address some of the problem areas mentioned above.
He did mention that all employee parking will soon be moved to the laydown yard.
Tracking Control12/8/201412/8/201412/8/2014APART
DetailsAndy J. Long
Significant trackout at both construction access points and onto surrounding roads

Correction:
Main access road through site needs good cleaning and need to designate staging areas or parking areas to reduce amount of dirt on this road.

Some issues will be taken care of by the regular sweeping that is occuring, but will need to take advantage of the drier conditions this week to prevent future issues.

Will monitor next few days to see if conditions improve.
General Inspection11/24/201411/24/201411/24/2014 PASS
DetailsAndy J. Long
Terraces perimeter was swept and cleaned this morning and is in good condition at the moment. No ongoing trackout occuring and silt fence is still installed and effective.

Considering the mud after recent snowmelt, site is in very good condition with no discharges or erosion issues observed.
Random Inspection11/7/201411/7/201411/7/2014PPART
DetailsAndy J. Long
Perimeter BMPs and inlet protection are installed and satisfactory. The interior road is paved but very dirty, with rain the site would discharge muddy stormwater. Site is said to sweep two times daily, but does not appear to be occuring. Unstabilized dirt at east entrance on Lysted is causing trackout and sediment accumulating in gutter.

Need to improve housekeeping and contain the sediment on Lysted street.
Tracking Control10/24/201410/24/201410/24/2014APART
DetailsAndy J. Long
No trackout to Council Springs observed. Silt fence and DI protection is installed.

Significant trackout from east acces point to Lysted leading down to round-a-bout and laydown yard.

Correction:

1. Continue daily sweep up
2. Install better vehicle tracking pad/stabilized construction entrance (dependent on installation of road through site....checking on schedule)
General Inspection10/10/201410/13/201410/13/2014APASS
DetailsAndy J. Long
Terraces of Boise surrounding streets and gutters are free of trackout from construction entrances and in the gutters. DI bags installed on all inlets with remaining capacity. Lysted St. has been temporarily patched to stabilze area in front of east side access point. No dust issues at time of inspection. No corrections required at this time.
General Inspection10/10/201410/10/201410/10/2014 CANC
DetailsAndy J. Long
rescheduled for Monday 10/13
Tracking Control9/9/20149/9/20149/9/2014PPASS
DetailsAndy J. Long
Perimeter streets around Terraces project have been swept as requested last week. Syman Company also maintained silt sacks in storm drains. No new trackout or ESC issues observed. Corrections complete
BMP Violation9/4/20149/4/20149/4/2014PFAIL
DetailsAndy J. Long
Need to follow up request for sweeping. No corrections observed during AM inspection rounds.

No significant sweeping or sediment cleanup has occured as requested. Correction notice sent via email to Petra-Terraces stromwater team.
Tracking Control9/3/20149/3/20149/3/2014PFAIL
DetailsAndy J. Long
Correction Notice:

1. Sweep Council Springs at west construction entrance as well as the first block Warm Springs to the west of Council Springs.
2. Sweep Lysted and install gravel bag where the pavement is not patched to collect loose sediment and rocks.

VM left to JC of Petra. Will follow up. Requested to complete by end of day 9/4.
Random Inspection8/12/20148/12/20148/12/2014PPART
DetailsAndy J. Long
Dust suppression in the northeast corner of project is inadequate. Dust blowing across Warms Springs towards the existing neighborhood.

Verbal CN issued to JC of Petra. An extra water truck has been designated to that area to increase efforts. Other sites through project have adequate dust suppression.
General Inspection8/7/20148/7/20148/7/2014 PART
DetailsEvan Jenkins
Some track out occuring on Lysted. Called Preston to disclose to him that a new construction entrance needs to be installed and Lysted needs to be swept around the round-a-bout
Complaint Inspection7/7/20147/7/20147/7/2014PPART
DetailsAndy J. Long
Complaint received regarding unreasonable amount of dust blowing off the Terraces site into trailer park north of Warm Springs.

Inspection observations:
1. Dust crossing Warm Springs was visible all the way from Lucky 13 (Eckart & Warm Springs)
2. Water truck on site, but was not being used at time of inspection.

Verbal Warning issued to RP Preston Ellingford to increase water truck use or add an additional water truck to site. It may also be good to put a medium term dust suppresant or polymer on the main construction road. He stated the main issue is that the area between hospital facilities and the Greenbelt is being backfilled at the moment and the vehicle movement and dumping of dirt make dust control difficult.
Random Inspection6/26/20146/26/20146/26/2014PPASS
DetailsAndy J. Long
Terraces project is in good condition. Light suppressed dust and water truck is on site, but traffic has also decrease. Silt fence perimeter has no breaches, both entrance has heavy duty rock, permit and SWPPP on-site. There is some utility work on Lysted that is not yet patched over and is a small source of loose sediment. Should be covered up soon.
Random Inspection5/27/20145/27/20145/27/2014APASS
DetailsAndy J. Long
Terraces project in compliance at time of inspection. No fugitive dust issues, both entrances have adequate stabilization and little trackout. Gutters looking clean. No corrections at this time.
Random Inspection5/13/20145/13/20145/13/2014PPASS
DetailsAndy J. Long
Observed that the correction discussed on Friday 5/9 has been completed.

DI on Warm Springs and gutter has been swept with sand and dirt removed.

Site is currently in compliance.
Tracking Control5/9/20145/9/20145/9/2014PPART
DetailsAndy J. Long
Received a complaint that there was significant trackout at site earlier in the day. Inspection of the site found that all perimeter roads had been cleaned and swept. No significant trackout observed at time of inspection (4 PM).



1 minor correction: DI on Warm Springs between Council Springs needs protection and the gutter swept. This should be completed early next week as discussed with JC from Petra.
General Inspection5/6/20145/6/20145/6/2014PPASS
DetailsAndy J. Long
Follow up inspection to see if action items from the 5/1 conference were completed.

Both entrances have new rock that is also extended. Very little sediment accumulation in gutters along Lysted. West entrance on Council Springs does not have any significant track out.

Site conditions are much improved. Need to check if DI on north side of Warm Springs between Council Springs and Eckert. Lots of sediment in gutters, unclear if it is from Terraces project trackout in preveious weeks - numerous projects are in the vicinity. Will follow up. No corrections at this time.
Site Preparation5/1/20145/1/20145/1/2014PCANC
DetailsAndy J. Long
Data entry error. Please disregard.
Conference5/1/20145/1/20145/1/2014APASS
DetailsAndy J. Long
Conference organized at Terraces' job site Main Office to discuss trackout issues from site and the Correction Notice (CN) issued on 4/30/2014.


Attendees:

Petra Inc: Brett Myron, John Low, JC Murray
City of Boise ESC: Evan Jenkins, Andy Long

Syman: Don Reynolds (SWPPP inspector)
All sub-contractor supervisors on the job



Summary: Petra organized a meeting at 8:30 AM on 5/1 to allow the ESC division to discuss track out issues with subcontractors on site. After the meeting we discussed plans to control trackout going forward and the corrections already made/in-progress.



Corrections made:

1. Round-a-bout on Lysted and entrance area on Council Springs have been swept and are in good condition.

2. Accumulated sediment in gutters has been scooped and removed manually.

3. Construction entrances to main site have been restored and lengthened, the staging yard entrance will be improved once more rock arrives

4. Subcontractors were made aware of the issue of trackout and how they can help reduce trackout.



Plans going forward:

1. The west entrance is only to be used for entry only in effort to prevent trackout onto Council Springs. The roundabout will be the main exit with the more serious trackout controls in place.
2. Street sweeping to occur 2 x daily.

3. A crew has been specifically designated to sweep and shovel the gutters where sediment accumulates.

4. Syman Co. will continue to make SWPPP inspections and email the stormwater team the corrections necessary (JC, Preston, Brett, John)
5. Boise ESC will always be sure to email entire stormwater team in addition to phone calls or conversations so everyone is aware of Correction Notices issued so they may be properly responded to.

With the corrective actions listed above and conference organized, the Terraces of Boise site is now currently in compliance.

Going forward the two ESC permits for Terraces will be:


ESC13-00755 : main site

ESC13-00793: staging/laydown yard
ESC13-00069 was issued prior to these permits and will be closed to simplify record keeping and communication. Note: This permit covered the acreage fees for the entire main site.
BMP Violation4/30/20144/30/20144/30/2014AFAIL
DetailsAndy J. Long
No improvements to construction entrance or a any efforts to reduce track out as listed in the SWPPP/ ESC plan.

Written CN posted on job trailer with 24 hour compliance request or possibility of SWO issued tomorrow.
BMP Violation4/29/20144/29/20144/29/2014PFAIL
DetailsAndy J. Long
Significant trackout. No corrections visible after multiple notices given to Preston (ISG) and JC (Petra) during previous week.

Went into job trailer and spoke JC. He explained some of the issues the site has been having with trackout. The amount of rainfall last week was exceptional and the entrance were not able to be restored as requested, which is understandable.

Idaho Sand & Gravel is supposed to restore both entrances and sweeping is said to be done daily but hasn't been very effective. Perimeter BMPs are good, but trackout due to degraded entrances and weak sweeping is the main problem.

Entrances and sweeping are supposed to be done this afternoon. Will continue to monitor.
Tracking Control4/25/20144/25/20144/25/2014PPART
DetailsAndy J. Long
Streets on both ends have been swept clean. The new construction entrances aren't replenished yet but were staked off to show where rock must be extended to. Big improvement over last few days.
Tracking Control4/24/20144/24/20144/24/2014PFAIL
DetailsAndy J. Long
No observable improvement in track out at both entrances. Pictures were taken. This is document continued non-compliance in regards to construction entrances and SWPPP narrative submited for permit.
BMP Violation4/23/20144/23/20144/23/2014PFAIL
DetailsAndy J. Long
Failed construction entrances need to be replenished with more rock. RP stated that the entranes do have fabric lining, though this is not confirmed.

Corrections:

1. Daily sweeping/mud clod removal
2. Install new entrances/maintain existing
3. Full road sweeping with machine

Note: Will need compliance by 4/29 (time limit given due to more anticipated rainfall).
Tracking Control4/4/20144/4/20144/4/2014PPART
DetailsAndy J. Long
Follow up on the Terraces project. Roads are being swept 1-2 times per day according to foreman JC Murray. Trackout at roundabout is not bad, but need to sweep entrance at Council Springs today.

JC stated that today more pit run is being brought in to increase length of constructions entrances at both ends, if not through the entire site.

Need to continue sweeping. Will check silt fences next week.
Tracking Control3/31/20143/31/20143/31/2014APART
DetailsAndy J. Long
Follow up inspection from CN issued Friday 3/28
.
Correction complete: Construction entrances were rebuilt and roads were swept and are in better condition than last Friday.

Corrections remaining:
1. Trackout still visible on all roads accessing site, need to increase sweeping or use different sweeping vehicle.
2. No wheel washing observed, unclear if wheel wash area situation was changed - were washing on top of construction entrance creating more mud.
Tracking Control3/28/20143/28/20143/28/2014PFAIL
DetailsAndy J. Long
Corrections required:

1. Sweep roundabout at main construction entrance and all the way to Warm Springs
2.. Sweep in front of western construction access
3. Restore construction entrances with rock
4. Provide alternate wheel wash area to prevent pooling at entrance.
Tracking Control3/18/20143/18/20143/18/2014PPASS
DetailsAndy J. Long
Follow up inspection from CN issued 3/14:

Roundabout and Lysted were swept and DI bags were checked. New construction entrance provided at west access point and looks good. Still need to improve east contruction entrance though there is no significant trackout currently.
General Inspection3/14/20143/14/20143/14/2014 FAIL
DetailsAndy J. Long
Perimeter of Terraces looks good, but need to sweep roundabout to Warm Springs and replenish construction entrance and drain puddle that is inside site before construction entrance.

Verbal CN issued to Petra RP Preston. History of response to corrections has been postive so far.
Tracking Control2/11/20142/11/20142/11/2014PPART
DetailsAndy J. Long
Verbal correction notice to RP Preston. Need to clean up Terraces project related trackout on roundabout in between site and laydown area and restore construction entrance as necessary. Rest of site BMPs are in good condition.
General Inspection1/22/20141/22/20141/22/2014 PASS
DetailsAndy J. Long
The Terraces Perimeter BMPs in good condition. Construction entrance preventing trackout. Approved.
General Inspection12/18/201312/18/201312/18/2013 PASS
DetailsAndy J. Long
Earthwork in progress. Perimeter silt fencing and construction entrance in good condition. No violations observed.
Site Preparation11/15/201311/15/201311/15/2013PPASS
DetailsAndy J. Long
jc Phone #: ###-####

All surrounding DI have filter bags installed. West, south, and east of site has trenched in silt fencing. Controlled access to construction area with single construction entrance at roundabout at Lysted and Arrow Junction. Site will be surrounded by chain link fence to protect equipment and BMPs. Site is ready for costruction. SWPPP, ESCP, and CGP permits were available for review. Approved.
General Inspection10/18/201310/18/201310/18/2013 NR
DetailsEvan Jenkins
Construction has not Started Yet