General Inspection | 6/3/2014 | 6/3/2014 | 6/3/2014 | | DONE |
Evan Jenkins
|
|
|
see final
|
DOC - Permit Finaled | 6/3/2014 | 6/3/2014 | 6/3/2014 | P | PASS |
Evan Jenkins
|
|
|
Project Complete Vegetation Re-established via sod/paving
|
General Inspection | 5/19/2014 | 5/19/2014 | 5/19/2014 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 5/2/2014 | 5/2/2014 | 5/2/2014 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 4/17/2014 | 4/17/2014 | 4/17/2014 | | PASS |
Andy J. Long
|
|
|
Path is complete. So materials and supplies still at staging site so will leave permit open.
|
General Inspection | 4/2/2014 | 4/2/2014 | 4/2/2014 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 3/18/2014 | 3/18/2014 | 3/18/2014 | | PASS |
Evan Jenkins
|
|
|
work back in progress Crew is preparing to pour the concrete for the greenbelt No ESC Issues at time of inspection. Site looks really good
|
General Inspection | 2/28/2014 | 2/28/2014 | 3/3/2014 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 2/13/2014 | 2/13/2014 | 2/13/2014 | | PASS |
Evan Jenkins
|
|
|
no activity at time of inspection
|
General Inspection | 1/29/2014 | 1/29/2014 | 1/29/2014 | | PASS |
Evan Jenkins
|
|
|
no activity at time of inspection
|
General Inspection | 1/14/2014 | 1/14/2014 | 1/14/2014 | | PASS |
Evan Jenkins
|
|
|
No Activity at time of inspection Appears they are waiting to pave the greenbelt
|
General Inspection | 12/27/2013 | 12/27/2013 | 12/27/2013 | | PASS |
Evan Jenkins
|
|
|
No Activity at time of inspection
|
General Inspection | 12/12/2013 | 12/12/2013 | 12/12/2013 | | PASS |
Andy J. Long
|
|
|
No activity. Western portion of Greenbelt is not yet complete. No corrections at this time.
|
General Inspection | 11/27/2013 | 11/27/2013 | 11/27/2013 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 11/8/2013 | 11/8/2013 | 11/8/2013 | | PASS |
Evan Jenkins
|
|
|
They appear to be preping to pave greenbelt
|
General Inspection | 10/24/2013 | 10/24/2013 | 10/24/2013 | | PASS |
Evan Jenkins
|
|
|
Contractor is currently laying down Sod for veg-reastablishment on the East Section of the project. West portion still under construction, in that the County and the City are conducting a joint pipe replacement for stormwater within the next few days according to the RP. So far, so good
|
BMP Violation | 8/6/2013 | 8/6/2013 | 8/7/2013 | P | PASS |
Kimberly M. Johnson
|
|
|
Citizen complaint received that construction has started. Permits have not been issued yet. Please post a SWO on site. Called Wendy Larimore at P&R and Jeff Arant at Diamond Contractors to notify. Construction supplies and equipment staged. Silt fence and straw wattle onsite but no active construction or earth disturbance has occurred. Remove double fee and SWO
|