General Inspection | 5/13/2014 | 5/13/2014 | 5/13/2014 | | PASS |
Andy J. Long
|
|
|
Finaled. See notes.
|
DOC - Permit Finaled | 5/13/2014 | 5/13/2014 | 5/13/2014 | P | PASS |
Andy J. Long
|
|
|
Road installation is complete and shoulders stabilized with gravel. All other permits finaled, ESC conditions satisfied.
|
General Inspection | 3/11/2014 | 3/11/2014 | 3/11/2014 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 1/8/2014 | 1/8/2014 | 1/8/2014 | | PASS |
Andy J. Long
|
|
|
No activity. Unable to assess stabilization status. Will revisit on next inspection. BLD permit is already finaled.
|
General Inspection | 11/8/2013 | 11/8/2013 | 11/8/2013 | | PASS |
Andy J. Long
|
|
|
Zeppellin and Harvard streets have been completed. No activity at time of inspection. Site has not yet acheived stabilization along sides of roads. No corrections required
|