Permit Information
Permit NumberESC13-00920
StatusFinaled
Name DARREN WOOD
Site Address 510 N COSTON ST
Project Name 
Customer Number 
ePlanReviewNo
Description
As per ESC conditions
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled5/7/20145/7/20145/7/2014PPASS
DetailsAndy J. Long
DI bag on Coston has been removed as requested. All ESC permit conditions have now been met.
General Inspection4/22/20144/22/20144/22/2014 PEND
DetailsAndy J. Long
All ESC conditions satisfied, but need to remove DI bag to the south on Coston. VM left with Wood Bros. Will check back.
General Inspection3/4/20143/4/20143/4/2014 PASS
DetailsEvan Jenkins
Landscaping almost finished. Some minor work still taking place. No ESC Issues at time of inspection
General Inspection1/15/20141/15/20141/15/2014 PASS
DetailsAndy J. Long
Working on laying new sidewalk - no sidewalk previously.. House complete yard not landscaped yet. Street is being kept clean during work. No corrections at this time. Will need to remove stormwater DI protection when complete/stabilized.
General Inspection11/29/201311/29/201311/29/2013 PASS
DetailsAndy J. Long
BMPs installed and permit posted visibly. No corrections at this. Most exterior and concrete work is complete.
General Inspection9/24/20139/25/20139/25/2013PPART
DetailsAndy J. Long
Luke Phone #: ###-####

Perimeter BMPs installed properly, MS4 drop inlet provided, and ESC sign has been completed and posted. Saw workers sweeping but there is still mud in the gutter. Needs to be swept and/or shoveled. Site is very small, no area for construction entrance.
BMP Violation9/25/20139/25/20139/25/2013ANR
DetailsMike Jordan
Corrections not yet made. Contractor on site getting ready to start.
Site Preparation9/24/20139/24/20139/24/2013PFAIL
DetailsJim Sly
C/N Stop Work....do not pour footing. Sign posted.....no writing on it. No protection of stockpiles. No prot. at sidewalk. No prot. of drain inlet. No secondary prot at gutter. No concrete washout pit. No pre eroision contr. insp. prior to excavation....started July 1st. Trackout.