DOC - Permit Finaled | 5/22/2014 | 5/22/2014 | 5/22/2014 | P | PASS |
Andy J. Long
|
|
|
West parking lot and stormwater swale is complete, landscaped, and stabilized. ESC permit conditions satisfied. BLD permit is still open, though no active construction.
|
General Inspection | 4/22/2014 | 4/23/2014 | 4/23/2014 | P | CANC |
Andy J. Long
|
|
|
Will check for final next General Inspection. Unable to inspect due to complaints/responses related to other site. Low risk site.
|
General Inspection | 4/22/2014 | 4/22/2014 | 4/22/2014 | P | CANC |
Andy J. Long
|
|
|
data entry error.
|
General Inspection | 4/22/2014 | 4/22/2014 | 4/22/2014 | | CANC |
Andy J. Long
|
|
|
Rescheduled for 4/23
|
General Inspection | 3/21/2014 | 3/21/2014 | 3/21/2014 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 2/18/2014 | 2/18/2014 | 2/18/2014 | | PASS |
Evan Jenkins
|
|
|
No ESC Issues
|
General Inspection | 1/15/2014 | 1/15/2014 | 1/15/2014 | | PASS |
Andy J. Long
|
|
|
New parking lot and drainage swale has been installed. Construction equipment still on-site with some grading and vegetation working remaining. All work contained within HP campus, access through Cloverdale gate. Perimeter wattles installed along portion of Chinden. No sediment leaving site. Approved.
|
General Inspection | 12/13/2013 | 12/13/2013 | 12/13/2013 | | PASS |
Andy J. Long
|
|
|
Project inside HP compound. No activity at time of inspection. Call Wes Smith RP for access. Project on hold till warmer weather. Pavement is laid but need to finish drainage swale.
|