General Inspection | 10/13/2014 | 10/13/2014 | 10/13/2014 | | PASS |
Evan Jenkins
|
|
|
see final
|
DOC - Permit Finaled | 10/13/2014 | 10/13/2014 | 10/13/2014 | P | PASS |
Evan Jenkins
|
|
|
complete no esc issues
|
General Inspection | 8/26/2014 | 8/26/2014 | 8/26/2014 | | PASS |
Andy J. Long
|
|
|
Eye Center is near completion. Parking lot is free of sediment and construction related spills. Needs landscaping and finishing touches. No corrections.
|
General Inspection | 7/11/2014 | 7/11/2014 | 7/11/2014 | | PASS |
Andy J. Long
|
|
|
WIP. McNealy Eye Clinic's frame is up. Project is on a pad with existing parking lot and stormwater drainarge. No trackout; trash kept in large container. No corrections at this time.
|
General Inspection | 5/26/2014 | 5/26/2014 | 5/28/2014 | | CANC |
Evan Jenkins
|
|
|
holiday
|
General Inspection | 4/8/2014 | 4/8/2014 | 4/8/2014 | | PASS |
Evan Jenkins
|
|
|
Left a new construction sign for contractor No ESC issues at time of inspection
|
Site Preparation | 2/18/2014 | 2/19/2014 | 2/19/2014 | P | PASS |
Jim Sly
|
|
|
|
General Inspection | 2/18/2014 | 2/18/2014 | 2/18/2014 | | PASS |
Alan Hauser
|
|
|
|