General Inspection | 4/29/2014 | 4/29/2014 | 4/29/2014 | | PASS |
Andy J. Long
|
|
|
Finaled.
|
DOC - Permit Finaled | 4/29/2014 | 4/29/2014 | 4/29/2014 | P | PASS |
Andy J. Long
|
|
|
House complete, landscaped and occupied. Lots of work ongoing on the block. BLD permit finaled, ESC conditions satisfied.
|
General Inspection | 3/28/2014 | 3/28/2014 | 3/28/2014 | | PASS |
Andy J. Long
|
|
|
WIP. Permits posted. Alley, streets, and sidewalks are relatively clean. A lot of houses being built on same block. No corrections.
|
General Inspection | 2/25/2014 | 2/25/2014 | 2/25/2014 | | PART |
Andy J. Long
|
|
|
Streets are clean and stockpiles in low risk area. Need to keep access alleyway clean.
RP stated sweeper will be coming this week. DI protection is satisfactory.
|
Conference | 1/22/2014 | 1/22/2014 | 1/22/2014 | P | PASS |
Andy J. Long
|
|
|
New Hunter Homes RP called and we discussed the site. Corrections issued previous Friday were completed.
He also stated that they will be fining sub-contractors not obeying ESC rules and have a weekly street sweeper service every Friday. Visual inspection of site was completed 1/21.
No further corrections at this time.
|
Tracking Control | 1/16/2014 | 1/16/2014 | 1/16/2014 | A | FAIL |
Andy J. Long
|
|
|
Written Correction Notice posted.
1. Clean up sidewalk and alley. Check filter bags. 2. Provide construction entrance for cement washout. 3. Empty washout, new washout should be lined and labeled.
Called new Hunter Homes RP Austin ###-#### to inform him. Compliance date 1/20/14
|
Site Preparation | 1/7/2014 | 1/7/2014 | 1/7/2014 | P | NR |
Jim Sly
|
|
|
Rollo
|
Site Preparation | 1/6/2014 | 1/7/2014 | 1/7/2014 | A | PASS |
Andy J. Long
|
|
|
Austin Phone #: ###-####
Permit posted. Will use Hunter Homes washout. Approved for construction.
|
General Inspection | 12/19/2013 | 12/19/2013 | 12/19/2013 | | PASS |
Andy J. Long
|
|
|
No activity or excavation yet. Permit is not posted. Hunter Homes to schedule Site Prep inspection when ready to begin.
|