DOC - Permit Finaled | 10/7/2014 | 10/7/2014 | 10/7/2014 | P | PASS |
Andy J. Long
|
|
|
Exterior landscaped and stabilized. Some work ongoing on interior. ESC conditions satisfied. No futher inspections required. Other Triplett townhomes still in progress.
|
General Inspection | 9/8/2014 | 9/8/2014 | 9/8/2014 | | PASS |
Evan Jenkins
|
|
|
no issues at this time
|
General Inspection | 8/7/2014 | 8/7/2014 | 8/7/2014 | | PASS |
Evan Jenkins
|
|
|
Framing near complete no esc issues at time of inspection
|
Site Preparation | 7/7/2014 | 7/7/2014 | 7/7/2014 | P | PASS |
Andy J. Long
|
|
|
Clint Phone #: ###-####
Permit posted. Tripplett Ranch townhome BMPs installed. Parcel is in between 2 existing homes under construction. Washout is lined and has 95% capacity remaining. Approved for excavation.
|
General Inspection | 6/30/2014 | 6/30/2014 | 6/30/2014 | | PASS |
Andy J. Long
|
|
|
Tripplett townhome developments currently in compliance.
|
General Inspection | 5/30/2014 | 5/30/2014 | 5/30/2014 | | PASS |
Andy J. Long
|
|
|
Triplett townhomes currently in compliance. No trackout, spills, or illicit discharges.
|
General Inspection | 4/29/2014 | 4/29/2014 | 4/29/2014 | | PASS |
Andy J. Long
|
|
|
No vertical construction yet. Triplett Ranch townhome sub is currently in compliance.
|
General Inspection | 3/28/2014 | 3/28/2014 | 3/28/2014 | | PART |
Andy J. Long
|
|
|
Corrections for Triplett Ranch:
1. Restore access to concrete washout 2. Install construction entrance to stockpile area in the center; or increase sweep out. Some track out is almost to the main road.
Verbal CN issued to RP Clint via phone. Will follow up next week.
|
General Inspection | 2/25/2014 | 2/25/2014 | 2/25/2014 | | PASS |
Andy J. Long
|
|
|
No changes since prior inspection. No activity. No corrections required.
|
General Inspection | 1/23/2014 | 1/23/2014 | 1/23/2014 | | PASS |
Andy J. Long
|
|
|
No activity at time of inspection - this section of Triplett Ranch is on winter shutdown. No corrections required at this time.
|
General Inspection | 12/19/2013 | 12/19/2013 | 12/19/2013 | | PASS |
Andy J. Long
|
|
|
No activity or ground disturbance.. Permit issued, but construction is postponed until after winter per RP Clint. Will schedule site prep when ready to excavate.
|