DOC - Permit Finaled | 7/16/2014 | 7/16/2014 | 7/16/2014 | P | PASS |
Andy J. Long
|
|
|
|
Aging Inspection | 7/16/2014 | 7/16/2014 | 7/16/2014 | | PASS |
Andy J. Long
|
|
|
Home construction is complete. Met RP Nick Holcomb on site to discuss project. He removed the DI bag and explained remaining tasks, which is only landscaping next week which will include final sweeping.
No further ESC inspections required, site is over 70% stabilized.
|
Random Inspection | 5/13/2014 | 5/13/2014 | 5/13/2014 | P | FAIL |
Andy J. Long
|
|
|
Trackout onto Woodcross for over 100 meters.
Verbal CN issued to RP Nick Holcomb. Will wait till VM is returned. Should be swept up by end of Wednesday and construction access improved if necessary.
|
Site Preparation | 11/20/2013 | 11/21/2013 | 11/21/2013 | A | PASS |
Jim Sly
|
|
|
Dave
|
Site Preparation | 11/8/2013 | 11/8/2013 | 11/8/2013 | P | PASS |
Evan Jenkins
|
|
|
Nick-Late afternoon please Phone #: ###-####
|