Permit Information
Permit NumberESC13-01045
StatusFinaled
Name JUSTIN REYNOLDS
Site Address 464 S WHISPERWOOD WAY
Project Name 
Customer Number 
ePlanReviewNo
Description
Per the attached ESC conditions
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Aging Inspection6/6/20146/6/20146/6/2014 PASS
DetailsAndy J. Long
Finaled.
DOC - Permit Finaled6/6/20146/6/20146/6/2014PPASS
DetailsAndy J. Long
House complete and landscaped. Contractor did comply by pulling permit ESC14-00172 for staging area. This area has been cleanerd, regraded and has started to vegetate.

ESC conditions satisfied.
BMP Violation3/10/20143/10/20143/10/2014PFAIL
DetailsAndy J. Long
RP did not pull a General Permit to clean up adjacent lot (440 Whisperwood) as requested on Friday 3/7. Sunrise Development LLC now has a hold placed on all its projects until all corrections for this site have been made.
BMP Violation3/7/20143/7/20143/7/2014PPEND
DetailsAndy J. Long
Met RP Justin onsite. He has until Monday morning 3/10 to acquire a general ESC permit for 440 Whisperwood and is to be responsible for grading and clean up for the mess made due to activities at this site. If not, a SWO and/or hold will be put on Sunrise Homes.
Site Final3/6/20143/6/20143/7/2014PCANC
DetailsAndy J. Long
data entry error. Disregard.
BMP Violation3/6/20143/6/20143/6/2014PFAIL
DetailsAndy J. Long
BLD already finaled but ESC conditions not satisfied.

Corrections:
1. Clean up trash and debris
2. Sweep sidewalks and street
3. Acquire permit for adjacent lot that is torn up from construction traffic. Regrade and stabilize as necessary.

If no action, all Sunrise projects will be placed on hold. Left message with RP Justin; awaiting a return call
Random Inspection3/5/20143/5/20143/5/2014PFAIL
DetailsAndy J. Long
No permit for adjacent staging lot and washout area. Muddy sidewalks, construction materials and waste still on site. no permit posted. BLD permit was already finaled but there is still work ongoing.
BMP Violation11/13/201311/13/201311/13/2013PPASS
DetailsAndy J. Long
Follow up inspection to SWO issued previous week.

Corrections made:

1. Clean up non-compliant cement washout
2. Sweep street and sidewalks
3. Clean up trash/debris
4. Restrict access to adjacent lots to prevent trackout
5. ESC permit posted
6. Existing filter bag DI protection is satisfactory

Actions:
1. SWO and activity hold can be removed
2. Contractor/RP to pay reinspection fee
BMP Violation11/6/201311/6/201311/6/2013PFAIL
DetailsAndy J. Long
Corrections not complete. Track out not completely cleaned.

Requirements:
1. backfill dirt next to sidewalk
2. cleanup existing washout and provide new washout
3. Post permit
4. Call for re-inspection

Reinspection fee will apply
Site Preparation11/5/201311/5/201311/5/2013PFAIL
DetailsAndy J. Long
Violations observed:

1. Work started prior to site prep inspection
2. No BMPs implemented
3. Trackout onto street
4. No ESC permit posted

SWO- stop work order in effect until following corrections are complete:

1. Sweep sidewalks road with trackout
2. Provide construction entrances
3. Install wattles at borders with sidewalk/driveway
4. Post ESC permit
5. Call in for re-inspection