Permit Information
Permit NumberESC13-01160
StatusFinaled
Name MATT FORRESTER
Site Address 2650 S ORCHARD ST
Project NameMAVERIK Convenience store
Customer Number 
ePlanReviewNo
Description
New MAVERIK convenience store with fuel pumps
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection3/16/20153/16/20153/16/2015 PASS
DetailsAndy J. Long
New Maverik is now fully lanscaped and stabilized. Temp BMP (DI bags) have been removed on Orchard and Malad. Hard surfaces swept and cleaned of loose sediment.

ESC permit coditions satisfied.
DOC - Permit Finaled3/16/20153/16/20153/16/2015PPASS
DetailsAndy J. Long
Site Preparation3/16/20153/17/20153/16/2015PCANC
DetailsAndy J. Long
data entry error
General Inspection2/12/20152/12/20152/12/2015 PASS
DetailsAndy J. Long
Maverik is complete and open for business. Need to install final landscaping and ground cover. No disturbed areas or issues.
General Inspection1/12/20151/12/20151/12/2015 PASS
DetailsAndy J. Long
New Maverik near completion. Interior work and some site landscaping is still in progress. All utilities and earth work are complete and parking lot is paved. No turbid discharges, uncontained stockpiles, or other violations. Permit posted on job trailer.

Final site cleanup and sweeping should occur before site final inspeciton.
General Inspection12/11/201412/11/201412/11/2014 PART
DetailsAndy J. Long
Inspection conducted at 11:30 AM...

New Maverik store, gas pumps & canopy, and paved parking lot have been installed. WIP on interior & exterior.

Site is in decent condition, though two corrections needed:
1. Sweep sidewalks and gutters on Malad and Orchard. (manual/broom sweep ok)
2. Protect stockpile near entrance on Malad with sediment control if it stays on site (note: RP Matt stated this pile is being off-hauled from site today)

Called RP Matt and issued verbal correction request. He stated corrections will be made asap.
Complaint Inspection12/11/201412/11/201412/11/2014PCANC
DetailsAndy J. Long
data entry error
General Inspection11/10/201411/10/201411/10/2014 PASS
DetailsAndy J. Long
WIP. Parking lot is about to be paved so construction entrance has been removed. Some minor trackout but DIs have sediment containment protection. No corrections required at this time.
Random Inspection10/9/201410/9/201410/9/2014APASS
DetailsAndy J. Long
Sidewalks and gutters surrounding new Maverik on Orchard are free of sediment accumulation. DI protection and silt fence perimeter provided. WIP. No dust or significant trackout. Permit is on job trailer.
Random Inspection9/11/20149/11/20149/11/2014PPART
DetailsAndy J. Long
Demolition occuring. Not dust control at time of inspection....

WIP. No dust control or water supply at site at time of inspection. RP Matt and site superviso Rich of Beniton Construction stated water is supposed to be used to help control demolition dust. While on site he went and stopped subcontractors and requested water control.

SWPPP is on site in trailer. No other issues at time of inspection. Will continue to monitor.
General Inspection8/26/20148/26/20148/26/2014 PASS
DetailsAndy J. Long
No activity or pre-construction mobilization at time of inspeciton. Old Hertz Car Sales is to be demolished and then parcel regraded and prepped for a Maverik.