Site Final | 4/29/2014 | 4/29/2014 | 4/29/2014 | P | PASS |
Andy J. Long
|
|
|
Discussed project with GC/RP Todd and homeowner. Homeowner is to complete landscaping. Driveway is compacted gravel. No trackout. Two permits for project, one to move a structure, the other is the new SFH.
|
DOC - Permit Finaled | 4/29/2014 | 4/29/2014 | 4/29/2014 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 2/6/2014 | 2/6/2014 | 2/6/2014 | P | PASS |
Andy J. Long
|
|
|
RP Todd onsite. Reviewed construction plans. No sediment leaving site. Permit posted. Approved.
|
Site Preparation | 12/2/2013 | 12/3/2013 | 12/3/2013 | A | PASS |
Andy J. Long
|
|
|
RP on-site to discuss BMPs. Parking and stockpiling contained within owner's property. Flat lot, berm, fence and vegetative barrier protect lake. Washout will be used for final pour.
|