General Inspection | 12/26/2014 | 12/26/2014 | 12/29/2014 | | PASS |
Andy J. Long
|
|
|
All site improvements at ITEC are complete including new warehouse and access drive.
BLD permit finaled, should be noted site is next to an active gravel pit and stone stockpiling business is adjacent to site and is not related to the construction.
ESC conditions satisfied, permit finaled.
|
DOC - Permit Finaled | 12/29/2014 | 12/29/2014 | 12/29/2014 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 11/10/2014 | 11/10/2014 | 11/10/2014 | | PASS |
Andy J. Long
|
|
|
ITEC building construction is complete and BLD permit has been finaled. Some related site improvents such as paving the access road to ITEC from Targhee is still in progress. No ESC violations or issues. Should be ready for site final next general inspection.
|
General Inspection | 9/23/2014 | 9/23/2014 | 9/23/2014 | | PASS |
Andy J. Long
|
|
|
WIP. No trackout or dust observed. Industrial site with no MS4 drainage or surface water. No corrections required at this time. Warehouse frame is up and entry road has been paved.
|
General Inspection | 8/8/2014 | 8/8/2014 | 8/8/2014 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 6/23/2014 | 6/23/2014 | 6/23/2014 | | PASS |
Andy J. Long
|
|
|
ITEC warehouse frame is complete. Construction is ongoing. No violations observed at time of inspection. No track out to Targhee and no dust issues.
|
General Inspection | 5/7/2014 | 5/7/2014 | 5/7/2014 | | PASS |
Andy J. Long
|
|
|
No discharges or sediment runoff from site observed. The site is next to a gravel pit, so unclear if all stockpiles are from this construction project. No trackout to Targhee. Approved.
|
General Inspection | 3/19/2014 | 3/19/2014 | 3/19/2014 | | PASS |
Andy J. Long
|
|
|
No ESC violations or fugitive dust observed. WIP. Approved.
|