Site Final | 7/14/2015 | 7/14/2015 | 7/14/2015 | P | DONE |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 7/14/2015 | 7/14/2015 | 7/14/2015 | P | PASS |
Mike Jordan
|
|
|
|
General Inspection | 6/1/2015 | 6/1/2015 | 6/1/2015 | | PEND |
Evan Jenkins
|
|
|
perm vegetation re-establishment
|
General Inspection | 4/14/2015 | 4/14/2015 | 4/14/2015 | | PASS |
Andy J. Long
|
|
|
No trackout or discharges offsite to Mitchell.
Installing carports for the 4-plexes so there are numerous stockpiles for the footings currently. Worker on site collecting stockpiles. Trash is contained. Materials being temporarily stockpiled south of new apartment building. Will need to clean/vegetate disturbed area to final ESC permit. No inlet protection provided on private stormdrain (connected to sand/oil interceptor) so will need to be pumped for routine O&M.
|
General Inspection | 2/27/2015 | 2/27/2015 | 2/27/2015 | | PART |
Evan Jenkins
|
|
|
trackout in parking lot that needs swept
|
General Inspection | 1/12/2015 | 1/12/2015 | 1/12/2015 | | FAIL |
Evan Jenkins
|
|
|
Trackout throughout the entire site. Unprotected stockpile in parking lot. Large quantity of debris scattered about that needs to be pickup and thrown away. Man hole in center of project has no protection. Corrections: 1.) Sweet area 2.) Protect Man Hole 3.) Pick up excessive debris throughout site. Called RP Scott and left VM disclosing issues. I expressed that he needs to contact me to discuss issues.
|
General Inspection | 11/25/2014 | 11/25/2014 | 11/25/2014 | | PASS |
Andy J. Long
|
|
|
4 plex in progress. Near completion. No ESC issues.
|
General Inspection | 10/10/2014 | 10/10/2014 | 10/10/2014 | | PASS |
Andy J. Long
|
|
|
|
Random Inspection | 8/25/2014 | 8/25/2014 | 8/25/2014 | P | PASS |
Andy J. Long
|
|
|
Frame for multiplex is up and no trackout to Mitchell; no spills or discharges observed. They are in proecess of installing new trench through parking lot, so will need to sweep once the trenching and asphalt cutting is complete.
|
General Inspection | 7/9/2014 | 7/9/2014 | 7/9/2014 | | FAIL |
Evan Jenkins
|
|
|
No construction signage posted. Parking lot needs to be swept and dirt ramp removed
|
Site Preparation | 5/22/2014 | 5/22/2014 | 5/22/2014 | A | CANC |
Mike Jordan
|
|
|
|
Site Preparation | 5/22/2014 | 5/22/2014 | 5/22/2014 | P | PASS |
Andy J. Long
|
|
|
Discussed project with RP Scott, whose office is across the parking lot of new building. Inspected previously. Ready for construction.
|
General Inspection | 5/20/2014 | 5/20/2014 | 5/20/2014 | | PASS |
Andy J. Long
|
|
|
No excavation started. Called RP and advised to install DI protection in parking lot and the MS4 south of the entrance on Mitchell and schedule site prep. Low risk site. Existing infrastructure/pads.
|