DOC - Permit Finaled | 9/15/2014 | 9/15/2014 | 9/15/2014 | A | PASS |
Andy J. Long
|
|
|
Completed Pine Tree Village townhome. ESC permit condition satisfied.
|
Aging Inspection | 8/14/2014 | 8/14/2014 | 8/14/2014 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 5/20/2014 | 5/20/2014 | 5/20/2014 | A | PASS |
Mike Jordan
|
|
|
|
Random Inspection | 4/7/2014 | 4/7/2014 | 4/7/2014 | A | PART |
Mike Jordan
|
|
|
Needs to sweep all hard surfaces of silts and pick up all construction debries. RP was notied.
|
Random Inspection | 3/21/2014 | 3/21/2014 | 3/21/2014 | P | PART |
Mike Jordan
|
|
|
Needs to sweep silts from hard surfaces and provide construction enterance/exit to avoid excessive trackout. As per RP, cleanup is being done at end of work shift.
|
Site Preparation | 12/23/2013 | 12/26/2013 | 12/26/2013 | A | PASS |
Andy J. Long
|
|
|
Jim Phone #: ###-####
Conference with RP Jim regarding 7 adjacent new townhome lots in Pine Tree Village phase #5. Site has perimeter BMPs, central washout, and signage to keep sub-contractors/delivery service off mud. Advised routine sweeping and trash removal. Approved for construction; will excavate when weather permits.
|