Site Final | 7/11/2014 | 7/11/2014 | 7/11/2014 | P | DONE |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 7/11/2014 | 7/11/2014 | 7/11/2014 | P | PASS |
Mike Jordan
|
|
|
|
General Inspection | 5/20/2014 | 5/20/2014 | 5/20/2014 | A | PASS |
Mike Jordan
|
|
|
|
Random Inspection | 3/21/2014 | 3/21/2014 | 3/21/2014 | A | PART |
Mike Jordan
|
|
|
Needs to sweep silts from hard surfaces and provide construction enterance/exit to avoid excessive trackout. As per RP, cleanup is being done at end of work shift.
|
Site Preparation | 12/23/2013 | 12/26/2013 | 12/26/2013 | A | PASS |
Andy J. Long
|
|
|
Jim Phone #: ###-####
Conference with RP Jim regarding 7 adjacent new townhome lots in Pine Tree Village phase #5. Site has perimeter BMPs, central washout, and signage to keep sub-contractors/delivery service off mud. Advised routine sweeping and trash removal. Approved for construction; will excavate when weather permits.
|