DOC - Permit Finaled | 5/15/2014 | 5/15/2014 | 5/15/2014 | P | PASS |
Andy J. Long
|
|
|
|
Site Final | 5/15/2014 | 5/15/2014 | 5/15/2014 | P | PASS |
Andy J. Long
|
|
|
This permit is for the site development phase of Boise Heights including dewatering, which is now complete. Vertical construction is under way and covered under ESC13-01231. The site is currently in compliance and will be closed.
|
Random Inspection | 5/5/2014 | 5/5/2014 | 5/5/2014 | P | PASS |
Andy J. Long
|
|
|
Perimeter BMPs and DI protection is good. No signifcant trackout on surrounding streets. No corrections at this time.
|
Random Inspection | 3/13/2014 | 3/13/2014 | 3/13/2014 | P | PASS |
Andy J. Long
|
|
|
Boise Heights phase I is in compliance. Construction entrance has an elevated grate bridge which can be used as a wheel wash. No sediment leaving site, DI's have protection. Did not detect any dewatering activities.
|
General Inspection | 1/17/2014 | 1/17/2014 | 1/17/2014 | | NR |
Evan Jenkins
|
|
|
No Site Prep Inspection Performed No Activity No Construction Signage No BMP's in place
|